Superconducting circuits: what remains to be done during hardware commissioning?

12 May 2005, 14:00
30m
864-1-C02 (CERN, Prévessin)

864-1-C02

CERN, Prévessin

Speaker

Reiner Denz (AT-MEL)

Description

The various steps of electrical quality assurance prior and during the powering tests will be discussed. Possible interference with the individual system tests of the quench protection and energy extraction system will be addressed. After a short review of the individual system tests prior to hardware commissioning, the test programme required for the proper qualification of the quench protection and energy extraction system will be presented. Finally an estimate of the necessary resources in case of equipment failure will be given.