Speaker
Antonio Perin
(AT-ACR)
Description
The DFBs, DSLs and connection cryostat, once installed and connected,
form an integral part of the magnet powering scheme as well as the
cryogenic system. This is reflected in the hardware commissioning.
The test activities comprise: pressure and leak tests, high voltage
tests (warm, before and after connecting and cold), instrumentation
checks, control procedure validation (including interlocks),
cryogenic operation with circuit powering (levels and temperatures,
steady state and transitory).
Author
Antonio Perin
(AT-ACR)