This talk will address the current status of the controls for the
LHC, the schedule for the procurement of the tunnel electronics and
control logic, the tasks associated with both the QRL reception test
and the full LHC sector commissioning, and will give some comments on
the feasibility with respect to the official LHC schedule. The
cryogenic instrumentation and controls are required for both the QRL
reception test and the full sector commissioning; unfortunately most
of the instrumentation and controls are different. This talk will
highlight the main differences between the two systems and the tasks
associated with the LHC commissioning, taking into account whether a
QRL has been previously commissioned in a given sector or not.