The logic of the different phases of the commissioning will be
reminded and the preparation will be briefly described. The day to
day organization in the field (control room, facilities, programme,
manpower for coordination, etc) will be discussed. The measures put
in place for personnel safety will be presented.
On the canvas of the different phases of commissioning, the instances
where decisions are required will be shown and the decision owner
will be identified. Communication channels inside the commissioning
community and towards the external world will be listed.
Based on the study of failure scenarios which was undertaken by the
working group, the identified showstoppers will outlined and recovery
and fall-back solutions –when they exist- will be suggested.