Conveners
Compatibility of Hardware Commissioning with Installation
- Claude Hauviller (TS-IC)
Katy Foraz
(TS-IC)
13/05/2005, 09:15
slides
The “proper” hardware commissioning will start once the machine and
experimental elements in the tunnel are installed and the individual
systems tests are done, in both sectors around an even point. This
implies co-activities between the two phases; as for example
individual systems tests (such as short circuit tests, etc.) will be
done during the installation phase without...
Daniela Macina
(TS-LEA)
13/05/2005, 09:35
slides
The installation of the experimental areas will be briefly reviewed
with particular attention paid to the installation of the radiation
shielding and vacuum beam pipes which may interfere with the Hardware
Commissioning of the magnets located close by (low beta triplets and
compensator magnets). The LHCb detector installation and the Hardware
Commissioning of the Cryogenic equipment...