Quality Assurance and documentation of results
- Felix Rodriguez-Mateos (TS-HDO)
-
Felix Rodriguez Mateos (TS-HDO)11/05/2005, 14:55slidesThe coordination for the Hardware Commissioning (HC) activities will involve the handling of a large quantity of documents (test sequences and procedures, technical notes, schedules, test results, etc) which must be related to both the hardware baseline databases and the general planning files. This talk will describe the main ideas on how all the information related to the...Go to contribution page
-
Davide Bozzini (AT-MEL)11/05/2005, 15:25slidesThe installation and commissioning of the LHC will produce a huge amount of data that will be collected and stored on different system databases. The MTF will bring together subsets of these data considered to be relevant for the traceability of test results during hardware commissioning. The talk will describe the interfaces between system databases and the MTF for the Electrical...Go to contribution page