Conveners
Electrical circuits and magnets (warm and cold) (cont)
- Frederick Bordry (AB-PO)
Reiner Denz
(AT-MEL)
12/05/2005, 14:00
slides
The various steps of electrical quality assurance prior and during
the powering tests will be discussed. Possible interference with the
individual system tests of the quench protection and energy
extraction system will be addressed. After a short review of the
individual system tests prior to hardware commissioning, the test
programme required for the proper qualification of the...
Hugues Thiesen
(AB-PO)
12/05/2005, 14:45
slides
The main topic of this talk is the validation of the warm part of the
electrical circuit (power converters and DC cables) before powering
tests with the magnets. In the first part, reception tests and
installation of equipments are presented: reception tests of power
converters in surface halls, installation of the power converters,
installation and initial tests of the DC cables....
Robert Harrison
(AB-CO)
12/05/2005, 15:30
slides
On reception of the hardware for each Warm Magnet Interlock
Controller (WIC) installation, the system will be constructed in the
lab. This will facilitate testing of the hardware and the correct
operation of the systems software and functionality. All input
signals will be stimulated and the expected response of the system
and the output for the respective power converter can then be...