The aim of this meeting is to get status of and issues with current
workpackages and to set out what everyone's doing over the next week.
1st June 2005, 12:00(CEST)/11:00(BST)
NPM MJRA4.6 status meeting:
* Actions from previous meeting
* Status of and issues with current workpackages
* Plans for current workpackages
* Holidays/Absences
CERN teleconference +41-22-767 7000, ask for EGEE JRA4.
Conference owner \"Ratna\".
The currently active workpackages are:
WP1: Revision of Metrics
WP1.1 Determine NOC/GOC requirements
WP1.3 Determine Middleware requirements
WP2: Diagnostic Tool Design and Development
WP2.1 Functional Specification
WP7: Test deployment
All items on going for duration of MJRA4.6
WP10: Integrate WP7 into gLite Source Control System
WP10.1 Create WP7 entries in gLite repository
Workpackages about to close are:
WP11: Correct issues from MJRA4.3
WP11.2 Resolve WP7/R-GMA issues