The 13th of August was the 2nd milestone of the InCA project. We had a 4-hour MD where we put all that was done so far into production. The goal of this exercise was to validate the whole architecture before moving to the construction phase of the project. I will report on what was in place that day and on the results we got. I will also report quickly on the other project’s activities before explaining the content of the milestone 3.