ETICS Technical Commitee

→ Europe/Zurich
TBD (CERN)

TBD

CERN

Alberto Di Meglio (CERN)
Description
Conference Name: ETICS Technical Committee meeting Recurrence: Every Thursday at 15:30 Dial-in numbers: +41227676000 (Main) Access code: 0126137 (Participant) Participant site: https://audioconf.cern.ch/call/0126137
    • 15:30 → 15:35
      Welcome and headcount 5m
    • 15:35 → 16:00
      Status reports 25m
      Highlights of the week, 5 minutes for each WP (NA2, SA1, SA2, JRA1, JRA2)
      • NA2 5m
        - Web site o We are still working on the content, most pages have content now and we are mostly tidying up the information to make navigation smooth and information clear. - Competitor analysis o Did not get much work on it this week as the there were other activities with higher priority. - QA&TEST 2008 o Adriano gave his presentation yesterday. It was followed with interest. Some participants approached Adriano for more information on ETICS and Grid-QCM. Collected some feedback. The conference will end on the 31st. - DNA2.3 o Working on the deliverable. We are currently in time with our internal deadlines. - Grid-QCM o Studied the pros and cons of changing Grid-QCM name into something else. The study results were presented to the PMB. PMB decided positively towards the change. Name proposed A-QCM where “A” stands for “Automated”. There is still the possibility to propose other names within today. If other names are proposed PMB will vote on the preferred one. o Training Preparing the list of topics for the demos. Added contributions coming from SA2.
      • SA1 5m
        Most of the time was spent to prepare for the release. Infrastructure: Release today - prepared for the upgrade to the ETICS repository - using the new RC release procedure: we have prepared everything on etics2 and etics2-repository - the new setup is ready and should be in production by the time the TC takes place Client Release postponed - unfortunately the release of the CLI has been separated from the rest of the system Resources: - is it possible to have the people at 25% on SA1 to come to CERN for 1 week every month? Packages Distribution: - YUM repository completed for the build dynamic repository. - Servlet for data visualization completed - Implemented byte-range download for the yum client Web interface/application: - Some small modifications done in the submission tab (when the popup panel is open all things in background get dark, the position of some elements inside the popup has been modified ). - Restarted development and maintenance of the Portal. Doing the main bug fixes and the requests (e.g. support more browsers). - Started to modify the client side and the web services in order to get, if the option is selected, the jobs where the current user is administrator. Release preparation completed - Integration of etics_R_2_1_0_0_RC3 , etics2-repository deployed and tested - Bug fixed for file copy in different AFS servers, migration of data from etics-repository completed - Plugged etics2-repository in etics together with etics-repository Testing the new release - The usal test bench has been executed on the etics2 setup and was successfull Deliverables: - Review received fro DSA1.2 (Eva) will send the new version this week - Starting the DSA1.3 (the SLA document for the ETICS services).
      • SA2 5m
        Support --------------- - Uwe/Michele in shift. 1 tickets in, 1 solved + 1 handled by Alberto on etics-support. - The support machine was hacked, and it's taking a while to get it back. We are going to move the site to a INFN provided Joomla site hosting, so in the future incindents won't take that long to recover from - Started working on enabling X.509 authentication for the support site Oct 31st Publish the support portal together with the web site Documentation ported to the support portal Both late, due to unavailability of etics-08. From the day the machine will be back on line, it's going to take 2/3 days to complete the work. I suggest the web site is published and then the support site will follow. Requirements ---------------- Nov 30th List of requirements to SA1 New Applications ----------------------------- - UNICORE porting, requirements analysis from aerospace applications, VDT porting. Nov 30th UNICORE, VDT, StoRM integrated Infrastructure Integration Job Submission ------------------------------------------- - Testing client almost completed. Early next week we will be bale to evaluate whether it's feasible to do the integration in the main service ourselves. Nov 15th Applied for ETICS VO Nov 30th Prototype for submitter service with Metronome Nov 30th ETICS VO created Evaluation ----------- - Defining the interviews format. Roles identified, questions decided. Will be sent to SA1 for iteration on Monday. Oct 31st Evaluation process definition Nov 15th Feedback on deployment automation to SA1 Nov 30th Interviews
      • JRA1 5m
      • JRA2 5m
        The development of both the TestSystem and the Workflow manager is in schedule, we're progressing as discussed in Palermo. The TestSystem is scheduled for an end of October beta, the workflow manager's next milestone is further away. TestSystem___________________ Functionality is in place, we're currently tweaking the user interface and experimenting with some user interface changes. We've implemented a "Filter" function with minimal search capabilities to search among the Plugins. If the user management is in place we're planing to highlight the user's own Plugins for better visibility (or a possibility to show only the projects the user contributes to). Integration - upgrades for Etics_____ Next week we will start to work on the integration of the Workflow manager and the TestSystem. We want to discuss what is necessary for the Etics portal integration, and the client side integration as well. We already know we need some new features for the user rights management, we have already collected our requirements for user rights management of the TestSystem (basically we need the same right management as the build system has). Who's responsible for implementing it?
    • 16:00 → 16:20
      Milestones and planning check 20m
      Formal check of agreed milestones and planning
    • 16:20 → 16:25
      ETICS USIS (User Satisfaction Improvement Strategy) 5m
      Improving user satisfaction about usage of the ETICS services is critical. ETICS is often perceived as slow and difficult to use. This is due to a number of factors: 1) Need for technical improvements in speed and usability 2) Disinformation or third-party rumours 3) General resistance to adopt 'procedures' We need to understand what to focus on and have a plan to address this issue as a combination of technical enhancements, training and dissemination. Where to start?
    • 16:25 → 16:30
      AOB 5m