Q1 to TAS connection. Status (Individual alignment) & brainstorming.
  • BPM close to the experiment is exposed to the shower. Not guaranteed reliability,  Thibault Lefevre pointed that recent Hi-Radmat results showed too much noise, but results still to be fully analised/understood

Q1-TAS region:

  • would it be possible to move the doble pump inside the cryostat?
  • Ideally, BPM inside cryostat would go to green position. [C. Garion & V. Baglin]
  • Christian Boccard pointed out that currently  access is too complicate now (remove helium feeds, cables, etc)