Please find Issues from EGEE ROCs and general info in:
https://twiki.cern.ch/twiki/bin/view/LCG/OpsMeetingPps
2009-01-09: In order to improve the roll-out procedure of the BDII service
and to minimise the overall risk of service disruption we are looking for a production site running a top-level BDII to join the Release test process. Upon a new update of the BDII software in production the site would be requested to be the first to upgrade the BDII and to confirm that the updated service work as expected.
More info about release test procedures in https://twiki.cern.ch/twiki/bin/view/LCG/PPS_Release_Testing
Contact: pps-support@cern.ch
2008-11-09: Pilot service of SLC5 WN at CERN: in progress
* LHCb tests on the pilot pointed out some issues with the
gssklog mechanism when submitting from DIRAC3.
The issue apparently arises with the newer version of VDT distributed in the WN
Under investigation.
* In accordance with the plans,two production CEs are being reconverted to use SLC5
They will be made available for production next week (19th of Jan)
* Details about the pilot (including planning, layout, technical info) can be
found in the page https://twiki.cern.ch/twiki/bin/view/LCG/PpsPilotSLC5
* Details about the single tasks can be found in the tracker
http://www.cern.ch/pps/index.php?dir=./ActivityManagement/SA1DeploymentTaskTracking
specifically listing the subtasks of TASK:8350