- Marco/Uwe in shift. 7 GGUS tickets in, 3 on hold, 4 escalated. 5
requests to etics-support, closed. 1 requests for externals processed.
People in SA2 need to be made administrator for the externals project.
The next release will contains the agreed changes needed to have the
support team be able to process externals, which willr equire that
anyway.
- Quite a bit of open tickets for ETICS Experts, more than half of them
assigend to Alberto. It wouldn't be possible to deal with so much work,
even if he were not the project manager, the client maintainer, the PMB
and TC chair. As support manager I have concerned that it is possible to
continue like this.
Requirements
------------
- I'm late finishing up the list fo requirements. They're all there, but
I need so some reordering.
New Applications
----------------
- StoRM integration completed.
- VEGA working on the setting up the services at VEGA for the first
phase of the aerospace applications porting.
Infrastructure Integration Job Submission
------------------------------------------
- ETICS VO created. Now we need to talk to the EGEE people on how to
make available our resources to the infrastructure. Even without that we
have share for submitting jobs and start some work on the EGEE
integration.
- Installing a Metronome poll at CNAF to test the nmi-submitter
prototype. We are having some problems with that, to be clarified.
Evaluation
----------
- This task is on hold, after Marco effort, who worked on that, moved to
SA1. Unlikely that we will be able to do work on that before the hired
people will join INFN in February.
Milestones
----------
- Nov 30th List of requirements to SA1
Further delayed. Foreseen Jan 16 th.
- Nov 30th VDT
Furter delayed, foreseen Jan 23th.
- Jan 16th Deployment of NMI submitter for testing
Unlikely we are going to make it for tomorrow.