-HVAC

installation scheduled for March 21 to April 1.

 

-New exhaust connection

New exhaust pipes connection (I will propose April 27 MD if it is a short intervention, i.e few hours)

 

-more tables and chairs in control room.

Prepare plan of CR (Giuseppe)

 

-AIDA2020 funds for work at GIF:

NIcolas Zagadinis, Paolo Iengo, ATL-RPC, ... will provide possible candidates for the application.

 

---

-beam trigger scintillators:

probably completed this week. Installation next week.

 

-GIF exhaust will be upgraded soon (beginning April, to be confirmed by Frederic)

 

There are minutes attached to this event. Show them.
    • 09:00 → 09:10
      Update: reference person, patrol rights and status for each setup 10m
      Please send to me the file with the update information. Please let me know also in case of no change.
    • 09:20 → 09:40
      Beam Time 2016 20m
    • 09:40 → 09:50
      Position of setups in the bunker during 2016 10m
    • 10:00 → 10:05
      New day for GIF weekly meeting 5m
    • 10:10 → 10:15
      Run coordinator 5m
      Speaker: Antonio Bianchi (Universita e INFN Torino (IT))
    • 10:25 → 10:30
      AoB
      • 10:25
        AIDA2020: support to activities at GIF 5m