GIF++ installation and schedule meeting
-New exhaust connection (EN-MEF)
New exhaust pipes connection (April 27 10 am MD if it is a short intervention, i.e few hours.Stop all gas systems)
-more tables and chairs in control room.
Prepare plan of CR (Giuseppe)
-AIDA2020 funds for work at GIF:
NIcolas Zagadinis, Paolo Iengo, ATL-RPC, ... will provide possible candidates for the application.
---
-beam trigger scintillators
commissioning Monday 18
-Thursday (April 14th):
ATL-MM, CMS-RPC, ATL-TGC, ATL-RPC
TGC beam trigger installation (Henso)
concrete blocks back closed at 3pm.
-Friday (April 15th)
Source scan CMS-CSC and RPC to be confirmed.
-Next Thursday (April 14th):
ATL-RPC will probably need bunker open (Gigi will request to Giuseppe)
There are minutes attached to this event.
Show them.