AWAKE BPM hardware/software
Thibaut noted:
- Firmware being finalised : New memory map - week 19
- All hardware components have been received: Next steps
- Test in SPS of the analogue board - Week 19/20
- Cabling, mounting and testing FEs : week 21
- Moving VFC/patch panel : Week 21
- Lab setup for software development to be done asap : possibly by end of the week 19
- Plan for Tunnel Installation :
- FIP installation to be checked
- Main installation in TAG41 and test in tunnel : Week 22
- TS2: Week 23 finalised installation in TT41 : Impact to be done
- Next meeting in two weeks: 24th of May 2016
- Results from SPS tests
- Hardware and software status and readiness for installation
- Commissioning plans
Lars noted:
- Tunnel installation well advanced (Joel to check for WorldFIP and WBTN as last resort)
- Expect a realistic test bench in the lab before the end of the week
- New version of VFC firmware expected tomorrow (several changes ...)
- Another meeting to be planned in two weeks with results from SPS and Lab (+commissioning?)
- Juan recommends finding the maximum in the sigma signal and using a fixed number of samples on the delta from this