Nuria Catalan Lasheras19/03/2009, 12:00•What is new? •What needs to be repeated? Warm sectors, cold sectors, sector 34? •ELQA for 5 TeV: problems to go to 1.9 kV? Better to reduce the tests to 1.6 kV? •Monitoring during cool-down, what circuits, what sectors in parallel? •HV tests in case of late symmetric Q-detector installation? To be discussed with QPS experts. •Planning ELQA: One sector at the time? Stand alone first, arc later?Go to contribution page
-
Laurette Ponce19/03/2009, 14:00•Can we force signals to provide CryoStart and CryoMaintain – when is it permitted? How to ensure that no equipment will be at risk? •Can we mask CryoStart and CryoMaintain? Under what conditions? How to ensure that no equipment will be at risk? •When to block / unblock circuits? •What are the rules? Notification, approval, who is authorised to do it, ….. •How to document such exceptional...Go to contribution page
-
Knud Dahlerup-Petersen19/03/2009, 14:30•nQPS, impact – how to commission it? IST and powering tests •new software: QPS snapshots, splice resistance measurements •impact of upgraded UPS on QPS commissioning •anything new on old QPS?Go to contribution page
-
Antonio Vergara Fernandez19/03/2009, 15:00•When can we start? •How long will it take? •Before nQPS: early measurements of bad splices with Cryogenic calorimetric measurements in sector 23 and 45 – when and how? •How long from 4 TeV to 5 TeV? How many steps to be done? Impact on commissioning?Go to contribution page
Choose timezone
Your profile timezone: