MINUTES:
· General Information: from next week we should have in place the new structure (after nMPP/Mops, etc.). ACTION: Nuria is expected to report about this at next meeting.
· Approval of Previous Minutes: nothing to report
· Expected start of powering test: end of May with 80/120 A circuits
· BORIS Presentation on 600 A Powering Circuit Procedure:
The procedure was slightly modified compare to 2008 Version, what is changed is:
- PNO.a3: it will take more time (for splice check); ~ 15 min.
o Karl Hubert comment: he suggests increasing the duration of one of the two plateaus of PNO.a3 to at least to 20 min.
- U_DIFF will be used instead of U_RES for the off-line analysis of PNO.a4
- New proposal to for the “re-commissioning” classifying as “old” and new”, circuits that don’t need or need a full powering re-commissioning. In the proposed classification, “New” could identify circuits in which busbars were “open to air”.
Proposal to release 2 documents:
o A powering procedure for the all 600 A circuits (the “new circuit” powering scenario) with in appendix the special powering for the “old circuit” powering scenario
o A document classifying all the circuits of LHC in “new” and “old” for the next HWC 2009.
- The test plan for the “old” circuit commissioning circuits was shown: PCS is not anymore foreseen.
A WIDE DISCUSSION FOLLOWED WITH THE FOLLOWING MAJOR COMMENTS (not exhaustive list):
o Rob: he asked about sensitivity and results of PCS during HWC 2008:
ACTION: It will be asked to Walter to report at nMPP about this point.
o Karl Hubert: he remarks how it is dangerous to extrapolate that a circuit test that was OK in 2008 will be OK also in 2009 (see the case of RCO corrector circuit NC degradation). So, may be better to repeat completely 600 A powering procedure?
o Rudiger, Gianluigi, Boris, Mirko, Markus et al: various comment about re-powering policy. A proposal could be to re-do PCS for circuit that will be commissioned to a not “nominal” PNO but higher the a threshold value (300 A ?) or for circuits with EE, or for circuits that were completely warmed-up… Anyway for S2-3 (1st re-powering planned) we should have time to re-do the full procedure without skipping PCS.
o Policy of powering tests in PGC and other must be also take into account (see ex. EDMS 941796)
ACTION: point to be followed at next nMPP meetings
· GIORGIO Presentation on 60 A Powering Circuit Procedure:
Not major changes compare to version 2008 but:
- In PCC: I-EARTH max from 10 to 5 mA
- In PCC: dI/dt from 1 A/s to 0.5 A/s. It is not clear from where the request was originated
ACTION for Gianluigi: to clarify who was the requestor and why.
- Procedure should be available at end of this week.
· GIORGIO Presentation on 80-120 A Powering Circuit Procedure:
Not major changes compare to version 2008 but:
- In PNO.a1: automatic test analysis under consolidation (available at mid May)
- In PCC and PNO.d1:PCC: automatic test analysis under development (also available at mid May)
- Procedure should be available at end of this week.
- Markus comment: for 2009 powering it is proposed to skip the “CRYO-maintain” check at PIC level.
- Claude: he confirms that the parameter for CRYO-start and CRYO-maintain are the same; only thresholds changes.
· ANTONIO Presentation on DFBs re-commissioning/re-cooling procedures:
References for electrical aspects are the EDMS 755782 and 829797. They will be updated in two months time (not before) but FINAL DRAFTS dedicated to S2-3 and S4-5 will be available in time.
- Revised procedures will take advantage by feedback from operation and will follow HW changes and update of the systems.
- A list of decided changes, but not yet fully implemented was presented (see slides). Majority of the changes concern setting values of process cryo-valves and instrumentation.
- More extensive re-commissioning procedures will be needed for DFBLC/DSLC (S.3-4) and DFBAC LCM (in 2L).
ACTION for ANTONIO: a small presentation on this point is requested .
- New system of protection from condensation (dry-air) must be commissioned (it will provide a signal to CRYO-start)
- Temperature switches for pressure relief valves and CL terminals were added.
- DFBX: commissioning of new control system for CL terminals.
- Ramp rates for correctors of triplets will be checked. It is not expect to take major changes. ACTION:TBD on which sector do these tests (S. 2-3 ?)
Hugues comment: are the DFB commissioning times take into account in the general plan? (One week of work AFTER cool down and BEFORE ELQA (eventually small overlap). ACTION: Rudiger will check with Katy.
AOB: Details for the installation of the protective covers in front of the DFBs will be discussed between people concerned, mainly Antonio, Nuria and Amalia
Michele Modena, 29 April 2009