- 26.5.: final connection of water circuit.
- 29.5.: registration of switches in landb and connection of switches to IT star-point swich (provisory installation).
- 31.5.: power to all racks.
- 31.5.: water circulating. This must be done on Wednesday (MD) , since it may affect other installations in the North Area.
- 1.6. Cabling completed, hopefully. Basic tests of switching on/off computers.
- 26.5.- 5.6.: registration of computers in landb, installation of operating system
- 6.6. - 8.6.: uSystems experts on site. Connection of rack control units, regulations, fine tuning. It will be useful to discuss with them how to best setup the monitoring/control. Towards the end, we should be able to produce heat by running artificial stress tests on the computers, or at least on few racks, and verify the regulation.
- 9.6. - t.b.d.: development of control and monitoring system for the 18 racks (hw, plc, winccoa sw).
- ~9.6. : installation of 10Gbps network in 609.
- 12.6. - 13.6.: transfer of DAQ system from bdg 4 to 609.
- End June: arrival of long fibers to connect DAQ to first detector module in the so called “cold box".
- Mid July: SM fibers connection for EOS.
- Mid July: connection of NP04- DCS1 switch.
- End July: DAQ for "cold box" up and running.