Conference Name: ETICS Technical Committee meeting Recurrence: Every Thursday at 15:30 CET Dial-in numbers: +41227676000 (Main) Access code: 0126137 (Participant) Participant site: https://audioconf.cern.ch/call/0126137
    • 15:30 → 15:35
      Welcome and headcount 5m
    • 15:35 → 16:00
      Status reports 25m
      Highlights of the week, 5 minutes for each WP (NA2, SA1, SA2, JRA1, JRA2)
      • NA2 5m
        Exploitation and Sustainability • Most of the activities this week were focused on exploitation and sustainability. Discussed possible business plan for ETICS, finalized the analysis of the core of ETICS competitors. The activities performed and the outcomes will be presented during the AHM Exploitation/sustainability session at the AHM. • Prepared the draft agenda for the session Dissemination • Reviewed the article on ETICS written by a journalist from ICT Results
      • SA1 5m
        ++ Releases - Finally 2.4.3 RELEASED - The client 1.4.7 will be release asynchronously (soon). - Release descriptions are available here: https://twiki.cern.ch/twiki/bin/view/ETICS/SA1ReleasesContents ++ Development Same and more as last week. - Integrating new submitter, diff and disseminator in the Web Services. - Dashboard for a User Project is being defined. - Plug-ins integration is progressing but few stil missing to have all the AQCM metrics (next few weeks). - Plugins for Findbugs and JUnit fixed - CKJMPlugin completed and tested - lcov (asked by gLite) started plugin - Updated AQCM plugin wiki page by inserting an AQCM report created for a testSubsystem - Working on multi-node testing but is not progressing fast with all other activities ongloing. - Submitters integration progressing on the development environment. - Working on the Web Applications to support the configuration and launch of multi-node tests. ++ Infrastructure - VEGA Installation: Admin rights assignemnet/investigation and explanation send via e-mail - User Guide : writing WN installation chapter, - Released 2.4.3, intervention, Friday early morning well within the schedule. - Debian builds: memory allocation increased seems to address the issue - X-Site migration: mail exchange, bug in Condor to be fixed, new Condor release needed - waiting Becky is back ++ Planning and Documentation - For the AHM: . Plugins, AQCM reports . Disseminator, Metrics . Submitters . Multi-node-Testing . Dashboard
      • SA2 5m
        Support ------- - Claudio, Michele in shift. 1 tickets, 1 solved (4h) Infrastructure Integration Job Submission ------------------------------------------ - Still waiting for an help for installing software on the EGEE worker nodes. - Finalized installation of ETICS services at CNAF. Everything seems to be working now. - Problem nearly solved with submission to local EGEE resources. We narrowed the matchmaking to CE for which worker nodes gave succesful responses. Now we have an acceptable rate of success, at least enought to conmtinue the testing. - Good progresses in testing the integration with Andres. Cycle seems to be working now. As soon as we have an rpm we'll roll it in the services here and we'll be able to test everything form in here. - Still adding a description of the architecture and a description of each submitter. - Refactoring the metronome submitter to use the common components framework developed for the gLite submitter. Deliverables and milestone --------------------------- - DSA2.5 due PM15. Sent final version to TC on June 17Th. As agreed the sections on deploymnt and functional testing has been removed, and there is going to be an addendum later on. - MSA2.5 in progress, we will be able to close it as soon as we can test the all thing here at CNAF. Should happen within next week.
      • JRA1 5m
      • JRA2 5m
        Development GUI of the Test Tool Registration system is heavily under work. Information system part is done also a wiki is integrated. Workflow designer is also under work. The agreed changes are in place, xml generation is under work. Allhands-meeting testing session As I said last week we are preparing an one our session presenting the following topics deployment test scenarious that we perform for our development (Just Test Tool Registration) the modelled ETICS process for web service test using EMMA coverage tool transition of the deployment scenario to multinode approach new developments (Test Tool Registration System) workflow designer presentation Sztaki's desktopgrid project presentation (current status and multinode) Implementing our GWT application we realised that running acceptance test scenarious are missing. To fill the gap we started to investigate 'Selenium' - a web application test tool. More details on that issue in the comming weeks.
    • 16:00 → 16:05
      Review recommendations, user satisfaction survey, next all-hands, AOBs 5m
      Discussion on recommendations List of questions (almost) defined AH agenda: http://indico.cern.ch/conferenceDisplay.py?confId=60397
    • 16:05 → 16:20
      Deliverables, milestones and planning check 15m
      Formal check of agreed milestones and planning
    • 16:20 → 16:25
      ETICS USIS (User Satisfaction Improvement Strategy) 5m
      Improving user satisfaction about usage of the ETICS services is critical. ETICS is often perceived as slow and difficult to use. This is due to a number of factors: 1) Need for technical improvements in speed and usability 2) Disinformation or third-party rumours 3) General resistance to adopt 'procedures' We need to understand what to focus on and have a plan to address this issue as a combination of technical enhancements, training and dissemination. Where to start?
    • 16:25 → 16:30
      AOB 5m