MEDICIS Planning review

→ Europe/Zurich
26-1-022 (CERN)

26-1-022

CERN

Isolde visitors room
    • 16:00 → 16:05
      Robot/RCS/storage 5m
      Speaker: Jean-Louis Grenard (CERN)
    • 16:05 → 16:10
      Ventilation/cooling 5m
      Speaker: Alexandre Joel Broche (CERN)
    • 16:10 → 16:15
      PPS 5m
      Speaker: Eva Sanchez-Corral Mena (CERN)
    • 16:15 → 16:20
      Front End 5m
      Speaker: Stefano Marzari (CERN)
    • 16:20 → 16:25
      Magnet Refurbishment 5m
      Speaker: Maxime Dumas (CERN)
    • 16:25 → 16:30
      BI Box 5m
      Speaker: William Andreazza (CERN)
    • 16:30 → 16:35
      Interlocks 5m
      Speaker: Pascal Fernier (CERN)
    • 16:35 → 16:40
      Vacuum 5m
      Speaker: Dr Jose Antonio Ferreira Somoza (CERN)
    • 16:40 → 16:45
    • 16:45 → 16:50
      EL Cabling 5m
      Speaker: Georgi Minchev Georgiev (CERN)

      Installation ongoing:

      - Rack installation, cable tray installation between racks RY and cables for access, timing – to be finished this week (racks to be finished tomorrow).

       

      Installation to be prepared:

      - Connection of cables from Boris Tube – to be visited with equipment responsible after having power converters on place to identify exact position of cables (cable list attached for information to Julien and Stefano) – I have to arrange it with Stefano and Julien.

      - Cables for Julien Parra Lopez (around 62 cables) – still missing name and details (position of cables, type of connector) from EN/STI for around 50 cables.

      - Cables for Christophe Mitifiot – around 22 cables to be installed – needed confirmation if all cables go between HY01 and RY03 racks.

      - Cables for Vacuum – still not received DIC, vacuum needs some information.

      - Installation of cables trays in the bunker and from rack HY01 to other site of room to join with cable trays arriving to RY03 (cable trays to be integrated due to lack of space – waiting for feedback from Jean-Pierre and Vincent).

       

      For all remaining activities, we should foresee 2-3 weeks of work (depending on missing information and DIC).

      To be confirmed, but preferably to be done end of June and beginning of July if all missing information are provided soon.

    • 16:50 → 16:55
      peripheral shielding + trolley 5m
      Speaker: Keith Kershaw (CERN)
    • 16:55 → 17:00
      mechanical parts - beam line 5m
      Speaker: Yury Gavrikov (Petersburg Nuclear Physics Institut (RU))
    • 17:00 → 17:05
      Collection Box 5m
      Speaker: Stefano Marzari (CERN)
    • 17:05 → 17:10
      PLCs F End, box 5m
      Speaker: Christophe Claude Mitifiot (CERN)
    • 17:10 → 17:15
      Control Application 5m
      Speaker: Cedric Charrondiere (CERN)
    • 17:15 → 17:20
    • 17:20 → 17:25
      RP monitoring/Safety systems 5m
      Speaker: Joachim Vollaire (CERN)
    • 17:25 → 17:30
      General Integration 5m
      Speaker: Vincent Barozier
    • 17:30 → 17:35
      Laser systems 5m
      Speaker: Mr Vadim Gadelshin (Johannes Gutenberg University of Mainz)