ETICS Technical Commitee

→ Europe/Zurich
TBD (CERN)

TBD

CERN

Alberto Di Meglio (CERN)
Description
Conference Name: ETICS Technical Committee meeting Recurrence: Every Thursday at 15:30 CET Dial-in numbers: +41227676000 (Main) Access code: 0126137 (Participant) Participant site: https://audioconf.cern.ch/call/0126137
    • 15:30 → 15:35
      Welcome and headcount 5m
    • 15:35 → 16:00
      Status reports 25m
      Highlights of the week, 5 minutes for each WP (NA2, SA1, SA2, JRA1, JRA2)
      • NA2 5m
        Writing DNA2.6 resubmission (long-term sustainability strategy) and DNA2.8 Dissemination and Use of Knowledge Plan (Third Update). At the moment work is going as planned and the deliverables should be on time for the review process. Who are the reviewers? DNA2.7 ETICS Grid Quality Certification Model activity report has not been started. Actually there is not enough information to write a new deliverable on A-QCM. According to the original plans it should have included results from trial certifications. We suggest to delay it to when the results from trial certification have been collected and analysed. Wrote a contribution on ETICS for the EGEE09 publication. It will be send to PMB by today for comments and tomorrow it will be send to EGEE. A contribution on ETICS was published on ICT Results http://cordis.europa.eu/ictresults/index.cfm?section=news&tpl=article&BrowsingType=Features&ID=90778
      • SA1 5m
        ++ Releases - Testing 2.4.4 release and 1.4.8 client (fixes to VCSROOT, etc). - No releases this week. Working on the features agreed in Budapest. https://twiki.cern.ch/twiki/bin/view/ETICS/PlansAHMBudapest - Release descriptions are available here: https://twiki.cern.ch/twiki/bin/view/ETICS/SA1ReleasesContents ++ Development - Working on multi-node testing on all aspects involved (WS, repository, clients, etc) - Adapting the Web Applications to support the configuration and launch of multi-node tests. - No problems with Firefox 3.5 - Added CKJM's "WMC", "DIT", "NOC", "CBO", "RFC", "LCOM", "Ca", "NPM, Findbugs", "Findbugs rate", "Junit", "Junit rate" to Disseminator list of metrics available - Dashboard for a User Project is being defined, but no progress this week. - Working on bootstrapper on KVM abd doing a full execution with vmware+nmi. - VCSROOT critical bug fix (impossible to migrate a component to a different VCS) Database schema changed, moved date. Changed Web Services and Web App. - AQCM: "multi-language component" case: AQCM design now considers also this option, not only multi-language project or subsystem. This change will help us in partitioning AQCM certification per languag - Webapp: Multi-node tests, now possible to attach platforms to nodes. VCSRoot now editable for configurations - Plug-ins integration is progressing. Received a few but seems are not tagged in CVS and there are (not huge) problems. Minro changes from Jozsef but most of plugins are very good - Submitters integration progressing on the development environment.
      • SA2 5m
        Support ------- - Andras in shift, 3 ticket, 2 solved, 1 escalated. - Working to get Condor 7.2.4 to build on deb. Wisc provides binaries but gLite wants rpm and deb, which Wisc has only for RHEL4. So we need to build the thing on our machine. On deb5 there seems to be a problme with aclocal missig on the wn, email sent. - X.509 authentication for the support site available. Internal can test the module for commenting articles on the support portal New Applications ---------------- - VEGA attacching a SLES9 worker node to their ETICS, but the clinet got problems. Alberto knows, and said a fix will be in the upcoming revision, next week. Infrastructure Integration Job Submission ------------------------------------------ - Preparing configurations for the metronome and glite submitter, to be intergated in etics-dev. We got configurations that produces rpms, but we need MicheleDB to be back on Monday to test everything and write the installation instructions. Then we'll pass everything to Marian for the integration in the deployment mechanism. - UNICORE submitter deployment stopped by dificulty with installing the ETICS client on SuSE, see above. Andre' to ask FZJ for a spare machine where to install another distro for moving on (SuSE is the defajult at FZJ). - JoGC EGEE applications CfP deadline extended - EC2 submitter development slowly going on.
      • JRA1 5m
      • JRA2 5m
        Plugin development Checkstyle is on release, pmd and jccn will be released soon. ETICS Test System GUI version 1.0 is finished, as soon as the plugins are ready, it will be integrated on etics-dev.cern.ch Work on Vera++ and Cppcheck is ongoing. Both plugins are feature complete. Some work is needed to make them fit more with the already available plugins (see Checkstyle development this week). Sadly there's a problem with Vera++ that it needs a ~40mb library to build it. It would make the install very slow, maybe binaries for multiple platforms should be provided instead. Multinode New xml version has been sent for verification Robert is working on an article for DCABES 2009 conference http://dcabes.meeting.whut.edu.cn/DCABES2009 An abstract has been sent.
    • 16:00 → 16:05
      Review recommendations, user satisfaction survey, AOBs 5m
      Discussion on recommendations status First version of the online survey at: http://etics.web.cern.ch/etics/survey.htm
    • 16:05 → 16:20
      Deliverables, milestones and planning check 15m
      Formal check of agreed milestones and planning
    • 16:20 → 16:25
      ETICS USIS (User Satisfaction Improvement Strategy) 5m
      Improving user satisfaction about usage of the ETICS services is critical. ETICS is often perceived as slow and difficult to use. This is due to a number of factors: 1) Need for technical improvements in speed and usability 2) Disinformation or third-party rumours 3) General resistance to adopt 'procedures' We need to understand what to focus on and have a plan to address this issue as a combination of technical enhancements, training and dissemination. Where to start?
    • 16:25 → 16:30
      AOB 5m