PASTE meeting

→ Europe/Zurich
2-R-014 (CERN)

2-R-014

CERN

Andrei Tsaregorodtsev
Description
CERN, bat 2 R-014 To join the telephone conference, click here: https://audioconf.cern.ch/call/0122929 To dial in to the conference: a. Dial +41 22 7676000 b. Enter access code 0165202
Production and PASTE Meeting, 4th August 2009, CERN Chair: A.Tsaregorodtsev Minutes: S.Paterson CERN: P.Charpentier, S.Paterson, M.Rashid, V.Romanovsky, R.Santinelli, A.C.Smith, F.Stagni Phone: V.Fernandez, R.Graciani, M.A.S.Miguelez, R.Nandakumar, M.Sapunov, A.Tsaregorodtsev, A.Zhelezov Apologies: J.Closier 0. Ongoing Action List (94) - 23/09/08 - Andrew,Marcos - Using SystemLogging service for dynamic services status monitoring (Andrew to provide FTS example) (116) - 18/11/08 - Ricardo - steer the CPU related activities in DIRAC, document procedures, move to the HEP CPU units (122) - 13/01/09 - Ricardo,Vladimir - Develop specialized SAM Agent to track and report errors with regard to pilots (133) - 03/03/09 - Matvey - Provide request DB interface page (139) - 31/03/09 - Roberto,Stuart - Track and test glexec as it is deployed at the sites, put CE into production pending the official release (140) - 31/03/09 - Andrew - Formulation of procedure for how to treat banning of sites based on job requirements e.g. input data / staging... (146) - 21/04/09 - Vladimir,Joel - SAM SW installation logic by synchronizing shared areas with the CS SW specification. Should be complemented with the installed SW monitoring tools. (151) - 26/05/09 - Andrew - Update central components with optimized BK methods using file time stamps (161) - 07/07/09 - Alexei - define Production Request for ongoing production to allow its monitoring (162) - 07/07/09 - Ricardo,Andrei - document the TQ priorities algorithm (163) - 07/07/09 - Joel - investigate possible use of CERN backup tools for log files archiving. (164) - 16/07/09 - Matvey,Adri - Formalize and simplify the release procedure for new web portal pages (including regular DIRAC version updates) (165) - 16/07/09 - Ricardo - Add WMS accounting for visualization of 'time to running' and other accounting metrics (166) - 16/07/09 - Ricardo - Set up volhcb05 as the new certification machine (167) - 16/07/09 - Philippe,Ricardo,Roberto - Ensure new middleware bindings are available and start SLC5 commissioning on volhcb12 (168) - 04/08/09 - Matvey,Alexey - Release procedure for the web portal, ensure request page is in production (169) - 04/08/09 - Stuart,Vladimir - Continue SLC5 testing at the sites where this is available Completed Actions: Done - (111) - 14/09/08 - Alexei,Andrei - Production request page, file merging and associated data distribution implementation Done - (156) - 02/06/09 - Ricardo,Joel - Refine VO-box setup to minimize impact of updates and maintenance procedures 1. Action Updates - Action(94) - SystemLoggingDB example Ongoing, Marcos will make a tool available in CVS for this. - Action(111) - File merging productions & request page Stuart summarized that production templates for Reconstruction, MC09 and MC09 merging are in place. These automatically associate productions to requests and start them etc. The major required development would be to release this in the production web portal. It was noted that the pace of updates to the web portal did not match the releases of DIRAC, this procedure will be refined ( ACTION: Matvey, Alexey ). Adding the PDF to a twiki such that a 'help' button from the portal links there would be very beneficial. Philippe mentioned that the representation of numbers in the request page would be greatly improved with comma separated digits and Alexey agreed to put this in place. - Action(116) - CPU studies Ongoing. - Action(122) - Develop specialized SAM Agent to track and report errors with regard to pilots Ongoing. - Action(133) - RequestDB monitoring Matvey will circulate the link to the request summary page on lhcbtest for comments. Andrei will make a proposal on the restructuring of the portal menus. - Action(139) - gLexec testing after deployment at new sites The pilot exercise has been closed, Roberto reported some conclusions to Antonio. Still the deployment / configuration of glexec SCAS is not trivial. The aim of the second iteration of tests was to demonstrate that the environment saving script was working but this was not the case when tested at some sites until configuration issues were used. Other configuration problems at IN2P3 prevented even to run tests there. For the LHCb official statement it was agreed to convey that we could only run on the correctly configured sites with IN2P3 being a notable exception. - Action(140) - Banning faulty storage elements Ongoing, technically completed but Andrew will add scripts to streamline this process and is starting on the documentation. - Action(146) - SAM software distribution synchronization with the CS The new module was added to the SAM suite to check the requested software is installed, Vladimir reported problems with crashing jobs so Stuart agreed to investigate. - Action(151) - Update of central BK components with optimized methods Ongoing. - Action(156) - Refine VO-box setup to minimize impact of updates and maintenance procedures Raja will test his script against v4r17p1. Action closed. - Action(161) - Define Production Request for ongoing production to allow its monitoring Action closed. - Action(162) - Document the TQ priorities algorithm Ongoing. - Action(163) - Investigate possible use of CERN backup tools for log files archiving. Ongoing. - Action(164) - Web portal release procedure Ongoing. -Action(165) - Add WMS accounting for visualization of 'time to running' and other accounting metrics Ongoing, Ricardo is working on it. -Action(166) - Set up volhcb05 as the new certification machine RPMs were installed on volhcb05 (SLC4) but this caused inconsistencies. Ricardo would like to reinstall that machine from scratch in order to proceed, Roberto will contact FIO to arrange this. -Action(167) - Ensure new middleware bindings are available and start SLC5 commissioning on volhcb12 The bindings are present but still not working correctly. Stuart and Vladimir (were) volunteered to run small tests to run on the 5 SLC5 sites (with SLC5 native and SLC4 in compatibility mode). There was some discussion regarding voms-proxy-init and whether this works at all sites. 2. Production Status Report - Report from the Production meeting Still waiting for disk space (and removal of backlog of requests) before restarting. There are several new requests pending and others that look to have produced enough events should be validated before proceeding. Production validation should be added as a phase in the production cycle and an agent instrumented to check and resolve any inconsistencies. - Data destination SE definition Stuart reported that this was already resolved, new simulation productions will be created with the policy of attempting any T1 SE in the associated grouping before going to failover. - v4r18 release Andrei mentioned some production DB optimizations and other fixes are part of v4r18 which will be imminently released. - Production priorities discussion See discussion triggered on the lhcb-dirac mailing list. Andrei agreed to create a twiki with the summary of this discussion. 3. DIRAC Tasks Items discussed above are omitted from this summary. - Infrastructure monitoring (SAM,SLS,Dashboard) Roberto is producing a description of the SAM suite for site admins and other interested parties. Monitoring and infrastructure tests should be migrated to Nagios and this is also being investigated. Federico is almost ready to deploy the first iteration of his suite for gathering & publishing information on sites and resources etc. - SystemLogging The system logging database schema was updated, Andrei suggested dropping the existing schema and starting afresh with the new one. Marcos & Victor agreed this was fine. - Framework status Threaded tasks inside threaded tasks were causing a memory leak in the sandbox service and this is still under investigation. The proxy length issue fix should now be in place. - Web Portal Philippe asked the status of the BK web interface and Matvey conveyed that he was unsure how to save files. Andrew commented that the CS can be saved as a text file. - WMS status Andrei asked what was necessary in order to migrate purely to the new sandbox client. It was agreed to check with the Ganga developers to see if they are using the correct DIRAC client version before proceeding with this. Others at external sites, for example, would have to update their DIRAC installations. Philippe agreed to set up a distributed analysis meeting in order to check this. The WMS cleaning agent policy should be amended to not clean production jobs and a production cleaning agent should be put in place. - Services deployment ( hardware, configuration ) Discussions with IT people resulted in tests that could be made on volhcb14. A frontend machine was requested to place load on this DB backend. 4. AOB Meeting finished at 1pm.
There are minutes attached to this event. Show them.
    • 09:30 → 10:00
      Ongoing actions 30m
      (94) - 23/09/08 - Andrew,Marcos - Using SystemLogging service for dynamic services status monitoring (Andrew to provide FTS example) (111) - 14/09/08 - Alexei,Andrei - Production request page, file merging and associated data distribution implementation (116) - 18/11/08 - Ricardo - steer the CPU related activities in DIRAC, document procedures, move to the HEP CPU units (122) - 13/01/09 - Ricardo,Vladimir - Develop specialized SAM Agent to track and report errors with regard to pilots (133) - 03/03/09 - Matvey - Provide request DB interface page (139) - 31/03/09 - Roberto,Stuart - Track and test glexec as it is deployed at the sites, put CE into production pending the official release (140) - 31/03/09 - Andrew - Formulation of procedure for how to treat banning of sites based on job requirements e.g. input data / staging... (146) - 21/04/09 - Vladimir,Joel - SAM SW installation logic by synchronizing shared areas with the CS SW specification. Should be complemented with the installed SW monitoring tools. (151) - 26/05/09 - Andrew - Update central components with optimized BK methods using file time stamps (156) - 02/06/09 - Ricardo,Joel - Refine VO-box setup to minimize impact of updates and maintenance procedures (161) - 07/07/09 - Alexei - define Production Request for ongoing production to allow its monitoring (162) - 07/07/09 - Ricardo,Andrei - document the TQ priorities algorithm (163) - 07/07/09 - Joel - investigate possible use of CERN backup tools for log files archiving. (164) - 16/07/09 - Matvey,Adri - Formalize and simplify the release procedure for new web portal pages (including regular DIRAC version updates) (165) - 16/07/09 - Ricardo - Add WMS accounting for visualization of 'time to running' and other accounting metrics (166) - 16/07/09 - Ricardo - Set up volhcb05 as the new certification machine (167) - 16/07/09 - Philippe,Ricardo,Roberto - Ensure new middleware bindings are available and start SLC5 commissioning on volhcb12
    • 10:00 → 10:30
      Production issues 30m
      - Report from the Production meeting - Data destination SE definition - v4r18 release - Production priorities discussion
    • 10:30 → 11:00
      DIRAC tasks 30m
      - Infrastructure monitoring (SAM,SLS,Dashboard) - Framework status - Bookkeeping status - WMS status - DMS status - Production Management status o production job post-execution checks - VO-boxes - Web Portal - Services deployment ( hardware, configuration ) - Documentation
    • 11:00 → 11:10
      AOB 10m