    • 15:30 → 15:35
      Approval of the minutes 5m
      Speaker: Julie Coupard (CERN)
    • 15:35 → 15:40
      LIU-PLI Follow-up 5m
      • Follow-up on the SRRs and ECRs
      Speaker: Julie Coupard (CERN)
    • 15:40 → 15:55
      LIU-PS ECR PS-R-EC-0005 (EDMS 1839213) Installation of a 6th Power Converter for the 40 MHz and 80 MHz RF Cavities in the PS Ring 15m

      Installation of a 25 kV / 8 A power converter for PS RF cavities in building 355.

      Speaker: Louis De Mallac (CERN)
    • 15:55 → 16:10
      LIU-PS SRR PS-LJ-EC-0001 (EDMS 1551627) PS Ring 2GeV New Injection Septum and Bumper 15m

      Space reservation for the dismantling and removal of the current injection equipment in straight section 42, followed by the installation of the new eddy current septum based injection.

      Speaker: Michael Hourican (CERN)
    • 16:10 → 16:25
      LIU-PSB SRR PSB-LJ-EC-0010 (EDMS 1739923) New Magnet for Functional Position BT.BHZ10 15m

      This document aims to reserve the space for the new longer BT.BHZ10 magnet which will replace the existing magnet for 2 GeV operations. An ECR detailing the magnet modifications to the complete transfer line will be issued once the full integration study has been completed.

      Speaker: Antony Newborough (CERN)
    • 16:25 → 16:40
      LIU-PSB SRR PSB-LJ-EC-0011 (EDMS 1739968) New Magnet for Functional Position BTM.BHZ10 15m

      This document aims to reserve the space for the new BTM.BHZ10 magnet which will replace the existing magnet for 2 GeV operations. An ECR detailing the magnet modifications to the complete transfer line will be issued once the full integration study has been completed.

      Speaker: Antony Newborough (CERN)
    • 16:40 → 16:55
      LIU-PSB ECR CPS-LJ-EC-0005 (EDMS 1805620) LBE Line and Infrastructure Upgrade for the Linac4 15m

      This document, with CPS-LJ-EC-0002 & CPS-LJ-EC-0003, concerns the Linac4 connection with the PSB injection transfer line. The present LBE line shall be adapted to the 160 MeV H- transverse emittances of Linac4 beam replacing most of its equipment and installing new auxiliary infrastructure in the area.

      Speaker: Aurelio Berjillos Barranco (CERN)
    • 16:55 → 17:00
      AoB 5m