GIF++ installation and schedule meeting

→ Europe/Zurich
892/1-D20 (CERN)

892/1-D20

CERN

45
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

Attendance:
————

Giuseppe (DT-DD)

Mara C. (DT)

Katerina K. (CMS-CSC)

Ignacio (CMS-DT)

Salvador (CMS-RPC)

Philipp (CBM)

 

Vidyo:
----------

Marek (CMS-GEM)

Lisa B. (CMS-GEM)

Henso A. (ATL-TGC)

 

There are minutes attached to this event. Show them.
    • 09:15 → 09:25
      Review of beam weeks operation 10m
    • 09:20 → 09:30
      Plans for upcoming week 10m

      Wednesday 11.10: Opening of the bunker

      • sTGC installation upstream
      • if CBM is done with the program, all the setup will be moved out of the bunker.

      Monday October 16th: 

      • beam pipe installation -> all setups to be removed from the beam line
      • if CBM did not managed to finish on Wednesday 11th, all the setup will be moved out -. bunker to be open

      Today plan (filter scan) : Starting after the meeting

      Upstream: CMS-RPC 

      Downstream: CMS-CSC, CMS-DT, CBM

    • 09:30 → 09:45
      Muon Beam Time GIF 15m

      Planning of the dedicated muon beam time periods during 2017

    • 09:45 → 09:55
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

       

       

       

       

    • 09:55 → 10:10
      Infrastructure & Upgrades to the Facility 15m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      Ongoing Projects :

      • Upgrade of GIF Control System - Initial list submitted to DT controls group
      • Two Berthold probes to be available after October

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • Requirements during YETS and LS2 5m

        Rack cooling will not be available for the YETS.
        CMS-CSC to check if  local chiller is available, otherwise help from EN-CV is needed.

      • Upcoming Interventions 5m

        Material Door, cooling perturbations,

        To be scheduled :
        ----------------------

        Bunker door ready to be installed  - new door (3.2m high) agreed - installation "after October test beam" -> 1-2 days of irradiation OFF

         

        YETS : water cooling stop for basically the full end of the year stop.

      • New Extraction Line - Gas System 5m

        Requirements for the new extraction line

        Gas flow in a normal condition : 
        how many detectors are connected and how much flow are they using ?
        Foreseen development ?

        Leakage flow in an emergency situation :

        EX gas involved if any :

        Additional gas racks to be installed / connected (if any) :

    • 10:10 → 10:20
      Announcements 10m
      • New Announcements 5m
      • Annual GIF Meeting - September 28th 5m
      • IMPACTS for 2017 5m

        Guidelines for filling in IMPACT requests

        Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes). If your work is outside, please state the whole number of hours.

      • AOB 5m

        Gas  bill 2016 : please note that the EP-DT budget for GIF does not cover consumables.
        Gas used at the GIF++ will have to be paid by the consumer. We will start the TID's soon.

        Question from Barbara : How is the Argon/CO2 provided, and will this be charged to the user.
        To be clarified with Roberto & Fred.

        O2 contamination study - Roberto to comment.