GIF++ installation and schedule meeting
-
-
09:15
→
09:25
Review of beam weeks operation 10m
-
09:20
→
09:30
Plans for upcoming week 10m
Wednesday 11.10: Opening of the bunker
- sTGC installation upstream
- if CBM is done with the program, all the setup will be moved out of the bunker.
Monday October 16th:
- beam pipe installation -> all setups to be removed from the beam line
- if CBM did not managed to finish on Wednesday 11th, all the setup will be moved out -. bunker to be open
Today plan (filter scan) : Starting after the meeting
Upstream: CMS-RPC
Downstream: CMS-CSC, CMS-DT, CBM
-
09:30
→
09:45
Muon Beam Time GIF 15m
Planning of the dedicated muon beam time periods during 2017
-
Planning for upcoming beam times 5m
Planning for the October beamtime
-
Report from Downstream Field 5m
-
Report from Upstream Field 5m
-
- 09:45 → 09:55
-
09:55
→
10:10
Infrastructure & Upgrades to the Facility 15m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)Ongoing Projects :
- Upgrade of GIF Control System - Initial list submitted to DT controls group
- Two Berthold probes to be available after October
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
Upcoming Interventions 5m
Material Door, cooling perturbations,
-
New Extraction Line - Gas System 5m
Requirements for the new extraction line
-
10:10
→
10:20
Announcements 10m
-
Annual GIF Meeting - September 28th 5m
-
IMPACTS for 2017 5m
Guidelines for filling in IMPACT requests
Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes). If your work is outside, please state the whole number of hours. -
AOB 5m
Gas bill 2016 : please note that the EP-DT budget for GIF does not cover consumables.
Gas used at the GIF++ will have to be paid by the consumer. We will start the TID's soon.Question from Barbara : How is the Argon/CO2 provided, and will this be charged to the user.
To be clarified with Roberto & Fred.O2 contamination study - Roberto to comment.
-