GIF++ installation and schedule meeting

→ Europe/Zurich
892/1-D20 (CERN)

892/1-D20

CERN

45
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

Attendance:
————

Vidyo:

 

----------

There are minutes attached to this event. Show them.
    • 09:15 → 09:25
      Review of last week operation & plans for this week 10m
    • 09:25 → 09:40
      Planning for the comming weeks 15m

      Downstream :

      Filterscan :   CMS-DT  now - 15h
      ------------

      CMS-CSC :15h Source OFF for 1h
      Then 2.2 attenuation
      Source OFF 1h again

      EP-DT : request 1 h access

      Upstream :  2h filter scan
      -------------

      • Report from Downstream Field 5m
      • Report from Upstream Field 5m
    • 09:40 → 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      GEM : installation of new detector inside same frame.

      ALICE electronic board to return for 1-2 weeks.
      we will try to host it in the upstream area this time, possible hosted by the ATL-MM  - no news

       

       

    • 09:50 → 10:05
      Infrastructure & Upgrades to the Facility 15m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      Ongoing Projects :

      Retrieval of TIMBER values : Work in progress, but already available in beta version
      Test site : http://epdtdi-vm-01.cern.ch:8080/pytimber

      Additional values need to be collected/republished ?
              - REMUS  - to be included in GIF Display
              - XTDV - to be included in pytimber only
       

       

      • Gas Consumption 2017 5m

        Gas consumption 2017 has been covered by CERN.

         

      • Upcoming Interventions 5m

        -> We therefore restart normal operation after Christmas break on TUESDAY 09.01  - DONE

        Local AUG test : 5-7 March. Will be announced in more details when closer to the test.

        Annual Irradiator Maintenance : March 12-14 2018
        DSO Test : March 15 2018

        Field mapping campaign (?) proposed before/after Maintenance. ≈ 3 Days.

      • Requirements during LS2 5m

        YETS :  Cooling stop for basically the full end of the year stop.
        However, minimal cooling will be provided by EN-CV via special solution.

    • 10:05 → 10:15
      Announcements 10m

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • Muon Beam Time 2018 5m

        Update on the SPS Planning

      • IMPACTS for 2018 5m

        Guidelines for filling in IMPACT requests

        General Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

        NEW IMPACT needed for 2018. (All current IMPACTS will expire at Saturday 23.December)

        Special IMPACT needed for Christmas Closure.

      • New Announcements 5m
      • AOB 5m