BI YETS 17-18 Follow-up Meeting
Regular meeting to follow-up on BI YETS activities.
Please come if you have an activity in progress or due to start.
PS
LIU WS installed. 5 BPMs installed and FT16 MSF in TT2
BGI in SS82, operational WS and BTV MU41 next week.
TT2 limited access.
Jeroen wanted to remove 43 pre-amplifiers. He will not have time to do this all.
BLMs
6 detectors installed in PSB. Want to install more, but may have to remove them as the documentation is not ready.
SPS
Tune pickup mainineane in 2 weeks.
BSI in TT20 - not sure if this will happen. Not much time left.
DBLM is included in another IMPACT so can remove the line in red.
LHC
Concern that there is a vacuum problem in the BSRT sector - Gerhard will check this.
BCTDC is under modification - to be checked if this is complete.
Opening of vacuum sector in p7 for crystal collimation.
Christos says that CMS are asking for valve opening on 30/3/18, some extra days.
Manfred asks about re-cabling of BPMs - This will be discussed. 7 sectors baked.