GIF++ installation and schedule meeting

Europe/Zurich
42/R-001 (CERN)

42/R-001

CERN

10
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN), Federico Ravotti (CERN)

Attendance:

 

----------

 

There are minutes attached to this event. Show them.
    • 09:15 09:25
      Review of last week operation & plans for this week 10m

      Source OFF on Tuesday for access system matrix change (beam to NA).

      - Pipes for EP-DT installed under floor.

      Plans for this week :

      - Access of 15 min this afternoon 15h30

      Next week : 

            Access & Installations days Tue & Wed
            Filter scan day : Thu.

    • 09:25 09:40
      Planning for the comming weeks & Muon Beam Weeks 15m
      • Report from Downstream Field 5m
      • Report from Upstream Field 5m
    • 09:40 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

       

       

    • 09:50 10:05
      Infrastructure & Upgrades to the Facility 15m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      Ongoing Projects :

      Retrieval of TIMBER values : Work in progress, but already available in beta version
      Test site : http://epdtdi-vm-01.cern.ch:8080/pytimber

      Additional values need to be collected/republished ?
              - REMUS  - to be included in GIF Display
              - XTDV - to be included in pytimber only
       

       

      • Upcoming Interventions 5m

        Installation shielding needed for the electronic rack postponed to Wed April 4th.

      • Requirements during LS2 5m
    • 10:05 10:15
      Announcements 10m

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • Muon Beam Time 2018 5m

        Update on the SPS Planning

      • IMPACTS for 2018 5m

        Guidelines for filling in IMPACT requests

        General Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

        NEW IMPACT needed for 2018. (All current IMPACTS will expire at Saturday 23.December)

        Special IMPACT needed for Christmas Closure.

      • New Announcements 5m
      • AOB 5m