GIF++ installation and schedule meeting
-
-
09:15
→
09:25
Review of last week operation & plans for this week 10mFilter scan:- CMS DT 2 hours of high attenuation- EP-DT and CMS RPC short access after the meeting- CMS RPC: filter scan tomorrow afternoonGeneral:- next Wednesday CMS-RPC trolley will be moved in order to allow EP-DT-2 to move at about 3 m from source- question: will LHCb set-up stay inside bunker during irradiation period?
-
09:25
→
09:40
Planning for Muon Beam time 15m
- 09:40 → 09:50
-
09:50
→
10:05
Infrastructure & Upgrades to the Facility 15m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)Ongoing Projects :
Retrieval of TIMBER values : Work in progress, but already available in beta version
Test site : http://epdtdi-vm-01.cern.ch:8080/pytimberAdditional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only
-
10:05
→
10:15
Announcements 10m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
Muon Beam Time 2018 5m
Update on the SPS Planning
-
IMPACTS for 2018 5m
Guidelines for filling in IMPACT requests
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).NEW IMPACT needed for 2018. (All current IMPACTS will expire at Saturday 23.December)
Special IMPACT needed for Christmas Closure.
-
-