Speaker
Jan Uythoven
Description
During the 2006 SPS run problems with the SPS beam dumping system were
encountered. The newly installed beam dump block TIDVG showed strong
outgassing when high intensity beams were dumped on the block. This often
resulted in an interlock of the injection kicker system MKP located close to the
TIDVG and by this stopping the SPS operation. Possible cures for 2007 and
longer term options are presented. During the same period one of the two
vertical beam dump kickers MKDV suffered from high voltage breakdowns.
During the year the operational voltage of both MKDV magnets was lowered
significantly, giving a temporary solution to this problem. The disadvantages of
this operational mode are explained, together with the foreseen hardware
improvements to the MKDV kicker system for the short and long term.
Author
Jan Uythoven