Kick-Off Meeting

Europe/Zurich
Participants: S. Albright, C. Bracco, G.P. Di Giovanni, V. Forte, B. Mikulec.
 
 
Aim: 
  1. have an EDMS document with detailed plan for PSB commissioning after LS2: define list of beams and, for each of them, the required commissioning steps (including RF) ==> define a common planning with all the users.
  2. Provide the users with “beam readiness” compatible with PSB planning by the end of the year.
  3. Agree on which beams have to be ready and when with PS and SPS (still need detailed RF plans), coordination with Verena and Giovanni’s WG.
 
Actions:
  1. Chiara will send Bettina the original commissioning document with the few mentioned change (ASAP).
  2. Prepare new EDMS document environment (Gian Piero) 
  3. Prepare skeleton of new document to be discussed at next meeting (Chiara) 
  4. Start functional specifications document for longitudinal painting and interface with Philippe (Simon and Vincenzo). In particular interlocking and injection synchronisation.
  5. Send invitation for weekly meetings every Tuesday morning starting on September 4th to PSB supervisors, Chiara (Chiara)
  6. Setup indico page (Gian Piero)
 
Topics for future discussions :
  • Production of LHCINDIV and LHCProbe  (see if the 500 ns is a strong limitation)
  • Plans for 1.4 GeV and 2 GeV cycles 
  • Flat-bottom injection for ISOLDE.
There are minutes attached to this event. Show them.
    • 1
      Kick Off Discussion