GIF++ installation and schedule meeting

Europe/Zurich
892/1-D20 (CERN)

892/1-D20

CERN

45
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN), Federico Ravotti (CERN)
There are minutes attached to this event. Show them.
    • 09:15 09:25
      Review of last week operation & plans for this week 10m

      Yesterday summary :

      Upstream :

      =========
      ATLAS-MM : left until January, in preparation area for the moment (RP checked)
      CMS-CSC small chamber hosted on LHCb setup at 3.5m
      ALICE TPC at 2 m unshadowed
      EP-DT2 : 5m next to CMS-RPC
      CMS-RPC : Trolley 1 at 5m, Trolley 3 at 4m

      Downstream :
      ==========
      CMS-GEM 1+2 : 1m
      EP-DT1 : 1.5 m
      ATLAS-RPC : 2.5 m  (back in bunker)
      CMS-CSC 1 : 2.5 m
      CMS-CSC 3 + LHCb : 5 m
      CMS-DT : suffering from gas issue.

       

      Filter scan :
      =========

      Upstream :

      EP-DT2 : filter 100 for 6-7h starting at 9h
      CMS-RPC : want 2.2 for whole week. 6.9 for two hours (after EP-DT)
      CMS-RPC : 1-2h source off
      ALICE : full field for 1h  around 16h

      Downstream :

      CMS-DT: 5h in range 460-22

      Access 1.5h planned after 17h.

       

      Access on Friday :  1.5h  afternoon

       

       

       




       

    • 09:25 09:40
      Mass Production Test Schedule 15m

      Upstream field :

      ATLAS-MM :   LM2  out   - comes back next year Jan/Feb.
                                SM1 &  SM2  out until Jan.
                                starting from January 4 chambers per months  - 2 / 4 chambers at the same time  ≈ for 1 year.

      ALICE TPC : 6 chambers, (3 big, 3 small)  - 2 at the same time, swap takes 45 minutes.
                     test restarted (unshadowed)
                     Total 20-30 (aiming for 6 per week,  1 day flushing, few hours for testing)  - 5 weeks

      Downstream :

      CMS-DT  1/15 campaign until early January.

      ATLAS - sTGC :  5-6 chambers should arrive beginning of mid January - half an hour for each chamber
                (might be better compatible with upstream)                 
       
      ATLAS-RPC : two gas gap chamber to arrive next week
    • 09:40 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      ALICE - FE Electronic upgrade. To be defined.

    • 09:50 10:00
      Infrastructure & Upgrades to the Facility 10m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      New Items :
      ==========

      CERN wide power cut on 19.12 - 6h.

       

       

       

       

      Ongoing Projects :

      NEW retrieval of TIMBER values : Work in progress, but already available in beta version
      https://epdtdi-pytimber.web.cern.ch/app/gifpp (also linked from main GIF page.

      Additional values need to be collected/republished ?
              - REMUS  - to be included in GIF Display
              - XTDV - to be included in pytimber only

      • Requirements during LS2 + Christmas 5m

        CMS-DT : Ar/CO2        70 l/h
        CMS-CSC : AR/CO2     10 l/h
        EP-DT : will let us know

        We potentially need a piquet from the user side. Access to be requested via TC.

      • Bunker Extension Project 20m

        Earliest start : End of April 2019

        Bunker layout is currently being finalized.

        To be decided : new position of the Irradiator

         

    • 10:00 10:30
      Announcements 30m

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • IMPACTS for 2018 5m

        Guidelines for filling in IMPACT requests

        General Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

        NEW IMPACT needed for 2018. (All current IMPACTS will expire at Saturday 23.December)

        Special IMPACT needed for Christmas Closure.

      • New Announcements 5m

        New GIF++ storage ready (0887-R-Q92). It will replace the 887-R-R86 and 887-R-R87

         

      • AOB 5m