Yesterday summary :
Upstream :
=========
ATLAS-MM : left until January, in preparation area for the moment (RP checked)
CMS-CSC small chamber hosted on LHCb setup at 3.5m
ALICE TPC at 2 m unshadowed
EP-DT2 : 5m next to CMS-RPC
CMS-RPC : Trolley 1 at 5m, Trolley 3 at 4m
Downstream :
==========
CMS-GEM 1+2 : 1m
EP-DT1 : 1.5 m
ATLAS-RPC : 2.5 m (back in bunker)
CMS-CSC 1 : 2.5 m
CMS-CSC 3 + LHCb : 5 m
CMS-DT : suffering from gas issue.
Filter scan :
=========
Upstream :
EP-DT2 : filter 100 for 6-7h starting at 9h
CMS-RPC : want 2.2 for whole week. 6.9 for two hours (after EP-DT)
CMS-RPC : 1-2h source off
ALICE : full field for 1h around 16h
Downstream :
CMS-DT: 5h in range 460-22
Access 1.5h planned after 17h.
Access on Friday : 1.5h afternoon
Upstream field :
ATLAS-MM : LM2 out - comes back next year Jan/Feb.
SM1 & SM2 out until Jan.
starting from January 4 chambers per months - 2 / 4 chambers at the same time ≈ for 1 year.
ALICE TPC : 6 chambers, (3 big, 3 small) - 2 at the same time, swap takes 45 minutes.
test restarted (unshadowed)
Total 20-30 (aiming for 6 per week, 1 day flushing, few hours for testing) - 5 weeks
Improvements needed or planned for the facility.
New Items :
==========
CERN wide power cut on 19.12 - 6h.
Ongoing Projects :
NEW retrieval of TIMBER values : Work in progress, but already available in beta version
https://epdtdi-pytimber.web.cern.ch/app/gifpp (also linked from main GIF page.
Additional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics
Guidelines for filling in IMPACT requests
General Guideline : One IMPACT per setup.
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
NEW IMPACT needed for 2018. (All current IMPACTS will expire at Saturday 23.December)
Special IMPACT needed for Christmas Closure.