GIF++ installation and schedule meeting
-
-
1
Review of last week operation & plans for this week
Yesterday summary :
Upstream :
=========
ATLAS-MM : left until January, in preparation area for the moment (RP checked)
CMS-CSC: small chamber hosted on LHCb setup at 3.5m
ALICE TPC at 2 m unshadowed
EP-DT2 : 5m next to CMS-RPC
CMS-RPC : Trolley 1 at 5m, Trolley 3 at 4mDownstream :
==========
CMS-GEM 1+2 : 1m
EP-DT1 : 1.5 m
ATLAS-RPC : 2.5 m (back in bunker) + second trolley to be moved in soon
CMS-CSC 1 : 2.5 m
CMS-CSC 3 + LHCb : 5 m
CMS-DT :Filter scan :
=========Thu 06th - access at 2pm for 1.5h
Upstream :
EP-DT2: filter 100 for 3h starting at 3.30pm
CMS-RPC : want 2.2 for whole week
ALICE : full field for 1h around 10.30amDownstream :
CMS-DT: 5h in range 460-22
============================================
Friday 07th: access of 1.5h in the afternoon
Upstream:
EP-DT2: 3 hours of source on with attenuation 1000 or more in the morning starting around 9am
Downstream:
CMS-DT will profit for having an attenuation 1000 upstream
=========================================================================
Monday 10th: access of 1h morning/afternoon depending on the results of the previous test (ALICE-TPC)
-
2
Mass Production Test Schedule
Upstream field :
ATLAS-MM : LM2 out - comes back next year Jan/Feb.
SM1 & SM2 out until Jan.
starting from January 4 chambers per months - 2 / 4 chambers at the same time ≈ for 1 year.ALICE TPC : 6 chambers, (3 big, 3 small) - 2 at the same time, swap takes 45 minutes.
moving to test 2 big chambers in parallel
test restarted (unshadowed)
Total 20-30 (aiming for 6 per week, 1 day flushing, few hours for testing) - 5 weeksDownstream :
CMS-DT 1/15 campaign until early January.
ATLAS - sTGC : 5-6 chambers should arrive beginning of mid January - half an hour for each chamber(might be better compatible with upstream)In addition : 1 chamber currently flushed in the preparation area, to be moved into the upstream area next week.
(to be confirmed on Monday)ATLAS-RPC : two gas gap chamber to arrive next week - 3
-
4
Infrastructure & Upgrades to the Facility
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)New Items :
==========CERN wide power cut on 19.12 - 6h.
Ongoing Projects :
NEW retrieval of TIMBER values : Work in progress, but already available in beta version
https://epdtdi-pytimber.web.cern.ch/app/gifpp (also linked from main GIF page.Additional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only-
a) Requirements during LS2 + Christmas
CMS-DT : Ar/CO2 70 l/h
CMS-CSC : AR/CO2 10 l/h
EP-DT : will let us knowWe potentially need a piquet from the user side. Access to be requested via TC.
Proposal : Stop of gas (except flushing) on Thursday 20.12 afternoon. -> User operation stopped before lunch time.
Restart of gas supply : Monday 7.01 -> User operation starting Tuesday
-
-
5
Announcements
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
a) IMPACTS for 2019
Guidelines for filling in IMPACT requests
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).NEW IMPACT needed for 2018. (All current IMPACTS will expire at Saturday 23.December)
Special IMPACT needed for Christmas Closure.
-
-
1