GIF++ installation and schedule meeting
-
-
09:15
→
09:25
Review of last week operation & plans for this week 10m
Restart of facility :
===============Gas systems available : Monday afternoon
Irradiator testing : Tuesday morning (see comments in Infrastructure section)
Facility operational : Tuesday 11h
Wednesday Installation :
ALICE arrived with 8 chambers, 2 in irradiation, 6 in corridor.
sTGC with one test chamber - 1 month test, running
CMS-RPC trolly 1&3
EP-DT2LHCb + CMS-CSC small prototype - IMPACT missing
CMS-GEM 1&2
EP-DT1
CMS-CSC
ATLAS-RPC - 2 setups, IMPACT missing
CMS-DT MB1&2
CMS-CSC + LHCb (IMPACT for LHCb missing)Pb blocks stored on the outside.
ALICE : 9h measurement - factor 1 for 1h
10h access for 1h to swap chambers.
Same for Saturday, Monday,
Tuesday 1h 9h-10h factor 1
otherwise 2.2 in upstream fieldFilter Scans :
==========Upstream : 6.9 for 2-3h, starting after the meeting
100 for 4-6h in the afternoon
Downstream : nothing announced.Access requests :
============1h requested by EP-DT Friday ->10:00 in combination with ALICE
-
09:25
→
09:40
Mass Production Test Schedule 15m
Upstream field :
ATLAS-MM : LM2 out - comes back next year Jan/Feb.
Starting from 23 January (latest 30.1), 2 chambers returning. In upstream area U1
5 filters 50->1 (= one morning).
ALICE TPC : 6 chambers, (3 big, 3 small) - 2 at the same time, swap takes 45 minutes.
moving to test 2 big chambers in parallel
test restarted (unshadowed)
Total 20-30 (aiming for 6 per week, 1 day flushing, few hours for testing) - 5 weeksDownstream :
CMS-DT 1/15 campaign until January.
ATLAS - sTGC : 5-6 chambers should arrive beginning of mid January - half an hour for each chamber(might be better compatible with upstream)In addition : 1 chamber currently flushed in the preparation area, to be moved into the upstream area next week. (to be confirmed on Monday)
ATLAS-sTGC: downstream, starting next week, half a day full field
swap to be synchronised with ALICEATLAS-RPC : two gas gap chamber arrived, to stay for January. -
09:40
→
09:50
New requests for tests at GIF 10m
introduction, goal of the test, plan, needs
-
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)New Items :
==========VISIT tour ! Next Wednesday 15h-17h as part of the BTTB7 conference.
Bunker extension :
==============Bunker layout frozen, final shape of roof will depend on available blocks.
Schedule floating, depending on availability of EN services.
Currently estimated start : Early July.
Ongoing Projects :
=============Correction of Irradiator Signals after power cut.
Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.PyTIMBER :
Additional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only -
10:00
→
10:30
Announcements 30m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
IMPACTS for 2019 5m
Guidelines for filling in IMPACT requests
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).NEW IMPACT needed for 2019 !
-
-