Present: Bettina, Alan, J.F, Fanouria, GP, Chiara, Federico
This meeting is now officially part of the LIU framework.
List of open actions available.
Commissioning document always available in EDMS, everybody can edit and complete it.
Strategy for commissioning beam: use minimum pulse length and possibly reduce the current in the LEBT to be around a few E9 H-, no need to be ppm.
RF commissioning draft plan prepared. There should be one method to produce LHCINDIV (high harmonic best way for shaving since it is faster, possible doing it at lower energy).
Not yet defined number of harmonics, GP asked to have it reported by Alan in a couple of weeks.
Need to ensure that adequate amount of time is dedicated for the ADT commissioning.
Next meeting: news about optics (Fanouria)
Need to define longitudinal painting for ISOLDE beams in case of different number of injection turns in the 4 rings (Simon, end of February)
There are minutes attached to this event.