GIF++ installation and schedule meeting

Europe/Zurich
892/1-B09 (CERN)

892/1-B09

CERN

30
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN), Federico Ravotti (CERN)
There are minutes attached to this event. Show them.
    • 09:15 09:25
      Review of last week operation & plans for this week 10m

      Weekly summary and plan for the next week :

      ALICE arrived with 8 chambers, 2 in irradiation, 6 in corridor.
      Friday, Saturday, Monday  :   8h30 Measurement with att. 1 then 1h access (9h30-10h30)
      Tuesday : 8h30-9h30 att.1 for 1h, otherwise 2.2 in upstream field
      Will continue until Mid-February (one week gap, with no chambers)

      sTGC with one test chamber - 1 month test, running
       - Upstream chamber QL1 taken out to preparation area
          2 chambers QS1 QS3 production chamber in upstream position
          (next Wednesday 2 x QS2 will come instead)

      CMS-RPC : installation of electronics for EcoGas, installation of chambers will happen next Wednesday.
      Currently using the default gas mixture.


      CMS-RPC trolly 1&3


      EP-DT2  & CMS-RPC :

             for the next days - repeatedly : 2h measurement with att. 100, then 2h no measurement (until 21h)
              will continue with different att factors for the next 2 weeks.

      LHCb + CMS-CSC small prototype

      ATLAS-MM :   LM2  out   - comes back next year Jan/Feb.
                                Starting from 23 January  (latest 30.1),  2 chambers returning. In upstream area  U1
                                5 filters 50->1 (= one morning).

      CMS-GEM 1&2


      EP-DT1
      CMS-CSC


      ATLAS-RPC - 2 setups, IMPACT missing   -
      next 6 weeks :  Wednesday 3 short accesses with after Source ON within 3h - after access day.


      CMS-DT MB 1&2 - to stop on 30.01 with 1/15 irradiation.
       

      CMS-CSC + LHCb  (IMPACT for LHCb missing)

      Pb blocks stored on the outside.




       

    • 09:25 09:40
      Mass Production Test Schedule 15m

      Upstream field :

      ATLAS-MM :   LM2  out   - comes back next year Jan/Feb.
                                Starting from 23 January  (latest 30.1),  2 chambers returning. In upstream area  U1
                                5 filters 50->1 (= one morning).
       

      ALICE TPC : 6 chambers, (3 big, 3 small)  - 2 at the same time, swap takes 45 minutes.
                      moving to test 2 big chambers in parallel
                     test restarted (unshadowed)
                     Total 20-30 (aiming for 6 per week,  1 day flushing, few hours for testing)  - 5 weeks

      Downstream :

      CMS-DT  1/15 campaign until January.

      ATLAS - sTGC :  5-6 chambers should arrive beginning of mid January - half an hour for each chamber
                (might be better compatible with upstream)
                In addition : 1 chamber currently flushed in the preparation area, to be moved into the upstream area next week. (to be confirmed on Monday)
           
      ATLAS-sTGC: downstream,  starting next week, half a day full field
                               swap to be synchronised with ALICE                  
       
      ATLAS-RPC : two gas gap chamber arrived, to stay for January.
    • 09:40 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      ALICE - FE Electronic upgrade. To be defined.

      EcoRPC-Gas chambers to be tested with new mixture for RPCs.
      - Discussion about installation ongoing.
       

      Test of sealing material / EN-CV for HL-LHC.
      One copper piece with pipes connected, expected to receive 10Gy, to be tested for 100Gy.

    • 09:50 10:00
      Infrastructure & Upgrades to the Facility 10m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      New Items :
      ==========

      Bunker extension :

      ==============

      Bunker layout frozen,  final shape of roof will depend on available blocks.
      Schedule floating, depending on availability of EN services.
      Currently estimated start : Early July.
       

      Ongoing Projects :
      =============

      Correction of Irradiator Signals after power cut.
      Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.

       

      PyTIMBER :

          Additional values need to be collected/republished ?
              - REMUS  - to be included in GIF Display
              - XTDV - to be included in pytimber only

      • LS2 restrictions & interventions 5m

        Restart of gas supply : Monday 7.01 -> DONE

        Access intervention :  next Wednesday morning.

        Update / Restart of the BE/CO infrastructure. 21-23.01

    • 10:00 10:30
      Announcements 30m

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • IMPACTS for 2019 5m

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

         

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

        NEW IMPACT needed for 2019 !

      • New Announcements 5m
      • AOB 5m