GIF++ installation and schedule meeting
-
-
09:15
→
09:25
Review of last week operation & plans for this week 10m
Weekly summary and plan for the next week :
Freon for RPC community - problem in gas barrack. Ventilation failed, in combination with low level the pressure could not be stable.
sTGC - problem with CO2 interlock. top of gas rack. (to be typed)
Problems with DIP values - linked to announced interventions by BE-CO and restarting of server infrastructure.
sTGC request : alarm on CO2 flow, we check with EP-DT-DI
------------------
ALICE arrived with 8 chambers, 2 in irradiation, 6 in corridor.
Friday, Saturday, Monday : 8h30 Measurement with att. 1 then 1h access (9h30-10h30)
Tuesday : 8h30-9h30 att.1 for 1h, otherwise 2.2 in upstream field
(this week in the afternoon due to ATL-MM 13h-15h)
Will continue until Mid-February.sTGC with one test chamber - 1 month test, running
2 chambers QS2 production chamber in upstream position
next week the 2 will be removed againATLAS-MM : Today chamber arrives in preparation zone.
If fine, chamber enters on Monday 9h-10h
Tues 4 h scan : 5 filters 50->1, followed by short accessCMS-RPC : installation of electronics for EcoGas, installation of 2 chambers on last Wednesday.
Currently using the default gas mixture.
CMS-RPC trolly 1&3
EP-DT2 & CMS-RPC :for the next days - repeatedly : 2h measurement with att. 100, then 2h no measurement (until 18 h)
will continue with different att factors for the next 2 weeks.
LHCb + CMS-CSC small prototype.
CMS-GEM 1&2
EP-DT1ATLAS-RPC - 2 setups, IMPACT missing -
next 6 weeks : Wednesday 3 short accesses with after Source ON within 3h - after access day.
CMS-DT MB 1&2 - to stop on 30.01 with 1/15 irradiation. will be OFF afterwards.
CMS-CSC + LHCb (IMPACT for LHCb missing)
Waiting for end of CMS-DT.
move MiniCSC back to downstream next Wednesday.Pb blocks stored on the outside.
Today filter scan : Upstream 100
Downstream CMS-DT
- 09:25 → 09:40
-
09:40
→
09:50
New requests for tests at GIF 10m
introduction, goal of the test, plan, needs
-
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)New Items :
==========Bunker extension :
==============
Bunker layout frozen, final shape of roof will depend on available blocks.
Schedule floating, depending on availability of EN services.
Currently estimated start : Early July.
Ongoing Projects :
=============Correction of Irradiator Signals after power cut.
Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.PyTIMBER :
Additional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only -
10:00
→
10:30
Announcements 30m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
IMPACTS for 2019 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).NEW IMPACT needed for 2019 !
-
-