IT-Protodune coordination meeting 14-02-2019
Room: Xavi, Ignacio
Remote: Stu, Denis, Geoff, Bonnie, Steve
IT services update
- CERN data centres hosts and services is being migrated from Lemon into Collectd. See Lemon retirement presentation: https://indico.cern.ch/event/790238/contributions/3282580/
- Migration of Phones in control rooms (Monday 18th at the IT-Auditorium): https://indico.cern.ch/event/798121
Round table
- protoDUNE-DP (Denis)
- All the optical fibers pulled, tested and certified
- Continuing tests with line buffer in the dark room
- Further problems with Wifi in the barracks with unstable connections
- Questions:
- Geoff: Georges from the Neutrino platform opened a ticket for the WIFI issues, and two APs were checked -> Denis to be added to the thread and future mails.
- Xavi: Did the "new" IN2P3 hardware arrived? plans /progress to install a local batch systems?
- Denis: Not yet. We have the nodes but need time to work on it.
- protoDUNE-SP (Geoff)
- Computing-wise things are stable. Two computers installed to handle the FELIX read-out. Timeline is not clear yet. This computers are not powerful enough and will need to be substituted later on
- The goal is to reconstruct the cold-box. They are setting out new fibers
- Still some HV issues being investigated. They need the readouts from inside the cryostat
- Getting back to SPSS scheduling and trying to look for a proper slot
- Introduced Bonnie: Online Computing coordinator and part of the SP DAQ community
- Stu: We are trying to armonize installation across all the different experiments.
- Questions:
- Xavi: Will you explore during this days the switch from Fermi FTS to CERN FTS?
- Steve: We want to do it but we don't have yet a clear timing for it. The intention is to do it before the 2nd beam run
- Xavi: (Steve and Jeff) Please thing about the plans long-term for the LS2 road map. Acton to prepare draft planing.
- Geoff: Need to think about a second data challenge to be have in the upcoming months?
- Steve: It was discussed during the meeting but there's not a fixed date yet.
- Xavi: Maybe it could be planned for end of May/beginning of June in order to perform it before DP is expected to be completed (July as target right now).
- Next Meeting in one months: tentative date 14th March