GIF++ installation and schedule meeting
-
-
09:15
→
09:35
Review of last week operation & plans for this week 20m
Weekly summary and plan for the next week :
------------------------
ALICE : 2 chambers tested last week; 2 chambers to be tested on Monday 11th when ATL-MM is done. The planning is the following: Monday 11/03 access around 9am. ATL-MM will remove the chamber and after that, Alice will start the test from 9:30am to 10.30am followed by a short access needed to remove both ALICE chambers. Next week on WED 13/03 other 4 small chambers expected. These last batch will conclude the ALICE test campaign.
ATLAS-MM : still continuing to test 1 chamber SM1 (module6), installed last week, till Monday 11/03 morning
Today filter scan started before the meeting for 3 hours and will continue tomorrow morning as well (from 9am) for 2-3 hours. During the filter scan period the configuration will be 22 to 4.6. Next week on WED 13/03 another chamber will arrive and will be installed inside the bunker (SM2 - module 7).EP-DT2 : 3hours in the afternoon (2pm to 5pm) for next week (filter from 22 to 10)
Otherwise : 4.6 filter for most of the week.
EcoGas - last chamber installed, staying on CMS-RPC gas mixture.
CMS-RPC : Scan this afternoon 6.9 - 3h starting at 3pm after CMS-CSC source OFF (starting after ATL-MM source scan). In case
Upcoming - 1 week test for FE electronics with priority for the access / bunker
Cosmic run with Scintillator / filter 2.2. or 6.9 - to be defined. Around ≈ 20. March.
New chambers arriving 20-25.03 - IMPACT to be donesTGC Production : return Mid-March
sTGC : QL1 test is over. Chamber removed from the bunker yesterday 06/03. QS2 installed yesterday 06/03 1h test this afternoon with attenuation 1 after ATL-MM is done (it shoud start at 1pm). 5h source scan (filter from 600 to 1) on Monday at 11am (after ATL-MM and ALICE are over with both tests and access).
CMS-GEM 1&2 : HappyEP-DT1: No comment
ATLAS-RPC : No special request for this week.
CMS-DT MB 1&2 : No comment.
LHCb : preparation to exchange chamber. Installing it next Wednesday.
CMS-CSC: Continuing radiation. Source OFF measurements today for 3 hours (after ATL-MM and ATL sTGC are done)
- 09:35 → 09:40
-
09:40
→
09:50
New requests for tests at GIF 10m
introduction, goal of the test, plan, needs
-
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)New Items :
==========Ongoing Projects :
=============Correction of Irradiator Signals after power cut.
Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.PyTIMBER :
Additional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only-
Bunker Extension Project 10m
News about the ongoing bunker extension
Bunker extension :
==============
Bunker layout frozen, work started already.
Next step : Re-arrange wall behind electrical switchboard
-> Announce power cut NEXT WEDNESDAY 13.02 at 9h for less than 2h. ->Due to a problem with a breaker upstream, the facility couldn't be restarted before 03.40 pmCurrently estimated start : Either early July or early September. (before or after August)
If we want July, we have to push now. -
Cosmic Trigger 10m
-
10:00
→
10:30
Announcements 30m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
IMPACTS for 2019 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).NEW IMPACT needed for 2019 !
-
AOB 5m
Issue with ligth. Button near access door should enable the light for additional 2h.
We plan to keep the light over the GIF area active in the near future (change by EN-EL needed) -> NOT FEASABLELocked door on Saleve side.
Proposal top remove the cylinder to avoid the guard locking the door during night times. -> Cylinder HAS BEEN REMOVED
-
-
09:15
→