Smoke extraction system with BE/ICS

→ Europe/Zurich
298/1-003 (CERN)

298/1-003

CERN

10
Show room on map
Michele Battistin (CERN)
    • 14:00 → 14:10
      Apave document 10m

      Document to be validated by Apave and prepared by EN/CV.
      The document describes EN/CV's technical solution for the smoke extraction installation and does a preselection of existing commercial products that could be applicable.

      Currently in draft version.

    • 14:10 → 14:30
      Power supply source for smoke extraction equipment 20m

      How the equipment will be supplied needs to be clarified.
      In the current design EN/CV has foreseen to supply the equipment from EN/CV's ABB switchboard.

    • 14:30 → 15:00
      Power supply voltage for equipment 30m
    • 15:00 → 15:15
      Safety requirements on cables & cable trays 15m
    • 15:15 → 15:20
      Inteface with SMSI 5m

      Clarification on the interface between the SMSI and the CV equipment.

    • 15:20 → 15:50
      Fan control 30m
      • Management of the fan speed
      • Management of the change-over between fans
    • 15:50 → 16:10
      Alarm transmissions 20m

      Management of alarm transmissions and position feedback of elements:
      - Fans
      - Dampers
      - Fire dampers

      Possible interface for fire dampers attached.