PSB Commissioning Meeting #18 (B-Train)

→ Europe/Zurich
774/1-014 (CERN)

774/1-014

CERN

12
Show room on map
Participants: GP, JF, Alan, Simon, A. Beaumont, Chiara, Piotr
 
Commissioning document: Piotr provided his contribution on optics, Federico’s part will follow and the transverse painting will be also re-discussed and an easier version prepared.
 
Commissioning of B-train
Pre-individual system tests: 
  • Installation for B-train system expected in Oct-Nov. 2019. 
  • For tests either the magnet has to grounded and the POPS-B locked out (or magnet disconnected). 
  • CV has to be started before the tests.
Different phases, time required, conditions and support are defined for IST (March 2020)  and HWC (April 2020). 
Important to test B-train with POPS-B and also MPS (as a possible backup solution).
Possible starting with basic low-level RF, no full functionality needed for the tests.
Need to share resources between PSB and PS => planning to be prepared accordingly.
 
Beam commissioning (mid September 2020):
  • Checks at injection, full cycle and energy matching (PS needed). 
  • Low intensity beam, e.g. LHCINDIV type
Small differences are expected between the different rings (mainly between internal and external ones). 
Detailed checks will be done for one internal and one external ring and for the remaining only a quick validation.
Possible working in parallel except for HWC of the  PS B-train (4 people).
BCT to be ready for commissioning with beam (need RF train).
 
A short discussion followed on the calibration of the new B-Train. Need to include a dedicated ZERO cycle for calibration (expected to be automatically launched every ~5 minutes, to be adapted depending on drifts measured in operation). A warning will be present to request a calibration if not performed for a certain time. The calibration lasts one cycle (~500 ms). In general it is expected to be able to operate the B-Train without re-calibrating it for a few hours. The number of hours will be evaluated with beam.
 
Action for Anthony: add all this information in the commissioning document.
 
Measurement device installed in spectrometer in Linac3, in switchyard region which will not be accessible for a while: when can this device be installed and tested? To be checked with Denis.