CERN, bat 2 R-014 To join the telephone conference, click here: https://audioconf.cern.ch/call/0165202 To dial in to the conference: a. Dial +41 22 7676000 b. Enter access code 0165202
Production and PASTE Meeting, 26th January 2010, CERN Chair: A.Tsaregorodtsev Minutes: S.Paterson CERN: P.Charpentier, J.Closier, Z.Mathe, S.Paterson, M.Rashid, V.Romanovski, R.Santinelli, A.C.Smith, F.Stagni Phone: V.Fernandez, E.Lanciotti, R.Nandakumar, M.Sapunov, A.Tsaregorodtsev Apologies: R.Graciani, A.Casajus 0. Ongoing Action List #10916 - Release procedure for web pages - pending an update from Adri #11223 - CREAM CE direct submission was pending a GridFTP server that allows to save pilot standard output #12526 - Joel mentioned that the LogSE machine is available but is not partitioned correctly, this is being investigated #13402 - Data access tests at DPM sites - Philippe commented that making use of Tier-2 sites that provide data storage requires an addendum to the computing model and agreement on the level of service a site should provide in this case. A proposal has been circulated for the approval of the OPG. #13403 - Elisa mentioned that the lhcbweb -> CERN connection could be enhanced by moving through the OPN but not by much (34->31ms). It was agreed to retain both instances of the web portal and investigate a load balanced alias. #13406 - Testing xrootd at IN2P3, it was agreed to formulate a testing module to make this kind of operation easier, this will be pursued. #13407 - LHCb platform detection and capability, tests are ongoing after a problem was found with install_project 1. Production Status Report - Current productions The minimum bias L0HLT1 Moore stripping and c inclusive stripping's are complete, b inclusive is pending 5 jobs (250 / 3k files). There were two passes of the V0.DST stripping productions that went smoothly from our side. A few small simulation requests for 2009 settings are pending, these initially failed due to a backwards incompatible change in the RICH detector description requiring a new Boole release. Andrew kindly agreed to take over in the absence of Stuart during the next week. 2. DIRAC Release Update - DIRAC Certification pre-release Andrei mentioned that the certification setup is complete, production tests have been running but we must start to define procedures for performing certification. - Certification tests o Bookkeeping usage for tests With one instance of the BK shared by development and certification it was agreed to use the namespaces /lhcb/certification and /lhcb/development to separate the activities. After a certification release is made we can trigger a cleanup of this namespace and for the next release candidate we reinstall the databases. o Failover usage for tests For testing request propagation it was agreed to install a request forwarding agent on volhcb14. o Integrated tests The whole chain of production is being tested in certification. Others are mimicking typical user activity. o Subsystem tests Certification tests by subsystem should be put in place in a common framework such that testing can be decoupled from the system responsibles. o Web portal tests A mechanism for testing the web portal such that it can be installed easily in certification should be defined. - Client tests (Ganga) For client tests using Ganga the client installation will be performed in $LHCBDEV on lxplus and configured to point to LHCb-Certification. For major releases the installation will be on hold pending the Ganga testing. For minor or patch releases the Ganga testing is only mandatory if the client is directly affected. - Preparing the new production system After some discussion it was agreed that the new major version of DIRAC should tentatively be made in mid-February (taking 1 day). This has to be coordinated very closely with the Ganga team. The current pre-release should be stable for the API so can be tested after installation in $LHCBDEV, hopefully today. In order not to complicate the new release with also coordinating a Ganga release it was proposed to add the old import structure temporarily to the SVN repository. Hot swapping of the production machine database is being tested in Barcelona but may not be ready for the first v5 release. DNS load balancing is also being investigated. 3. DIRAC Tasks - SVN migration o release tagging, building and installation scripts Joel asked whether the versions.cfg file will keep all previous tags. After a certification release moves into productions the intermediate tags will be purged. - Infrastructure monitoring (SAM,SLS,Dashboard) Roberto will try to use the updated unit test code from Andrew. - ResourceStatus System status Federico now has a common interface for his clients. There were several bug fixes for RSS components. The new notification system alarms were attempted to be used but do not appear to be deployed in development. The Notification DB should be updated simply by dropping the existing development DB. For keeping track of the current shifters and GEOCs the developer of the ShiftDB was contacted. This requires an Oracle connection to the database so Zoltan's wrapper classes can be utilised. Andrei mentioned that some of the RSS modules were in conflict in development, Federico will check. - Bookkeeping status No updates, there were a few bug fixes recently. - Production Management status Any LHCb specific code was removed from the Transformation system. There are now two places to retain production code including the Transformation system and LHCb Production Management system. 4. AOB Next week is a software week, there is a slot on Tuesday morning to discuss experiences with real data and the current status of the sub-projects. Andrei agreed to present the DIRAC v5 status. Philippe will coordinate the session and contact the prospective participants. Next week there will be no PASTE meeting due to the Software Week.
There are minutes attached to this event. Show them.
    • 09:30 → 10:00
      Ongoing actions 30m
      The task list is available via the Savannah DIRAC group ( Task List ). If you are not already registered please do so at the Savannah page. In order to streamline the time spent during PASTE on the actions list only tasks in the status 'ToBeDiscussed' will be discussed there. In case some actions fall by the wayside they will automatically be updated to this status. Therefore the action assignees should take care to update this. For ongoing actions it is advantageous to report any progress in the Savannah tasks each week.
    • 10:00 → 10:30
      Production issues 30m
      - Current productions
    • 10:30 → 10:50
      DIRAC Release Update 20m
      - DIRAC Certification pre-release - Certification tests o Bookkeeping usage for tests o Failover usage for tests o Integrated tests o Subsystem tests o Web portal tests - Client tests (Ganga) - Preparing the new production system
    • 10:50 → 11:20
      DIRAC tasks 30m
      - SVN migration o Development (volhcb12) System status o release tagging, building and installion scripts o Subsystems migration status - Infrastructure monitoring (SAM,SLS,Dashboard) - ResourceStatus System status - Framework status - Bookkeeping status - WMS status - DMS status - Production Management status - VO-boxes - Web Portal - Services deployment ( hardware, configuration ) - Documentation
    • 11:20 → 11:30