09:00
→
09:10
Introduction
10m
Speaker
:
Jan Uythoven
(
CERN
)
09:10
→
09:30
Overview of the present SMP System
20m
Layout of the present systems
Evolution of the system since first deployment
Dependability of the present system
Motivation to upgrade
Speaker
:
Ivan Romera Ramirez
(
CERN
)
2019_SMP_v2_Workshop.pdf
2019_SMP_v2_Workshop.pptx
09:30
→
09:50
Feedback from LHC Operation
20m
General Feedback on the SMP from LHC operation.
Changes related to b* reconstruction.
Bunch intensity as possible SMP requirement.
Speakers
:
Jorg Wenninger
(
CERN
)
,
Matteo Solfaroli Camillocci
(
CERN
)
SMP-review.LHC-op.June19.pdf
SMP-review.LHC-op.June19.pptx
09:50
→
10:20
Feedback from SPS Operation
30m
General feedback on the SMP from SPS operation.
New requirements: Intensity and Energy frames, Beam Presence Flag.
Review of SBF use in the SPS.
Bunch intensity as a possible required frame.
Speaker
:
Verena Kain
(
CERN
)
SMP_SPS_requirements_2019_v1.pdf
SMP_SPS_requirements_2019_v1.pptx
10:20
→
10:50
Coffee Break
30m
10:50
→
11:05
BI connections to SMP
15m
Plans for BI sources for SMP during LS3.
MTT module plans.
Bunch-by-bunch or max intensity as possible input to SMP
Speakers
:
Lars Jensen
(
CERN
)
,
Tom Levens
(
CERN
)
MPP-SMP2_BE-BI.pdf
MPP-SMP2_BE-BI.pptx
11:05
→
11:20
LS3 Plans for the Timing System and beyond
15m
Timing system plans for LS3.
Future use of White Rabbit.
Long-term support of CTRV module.
Speaker
:
Grzegorz Kruk
(
CERN
)
2019-06-21 Timing@SMP Review.pdf
2019-06-21 Timing@SMP Review.pptx
11:25
→
11:50
SMP v2 Hardware Implementation and Timeline
25m
SMP v2: new requirements.
Considerations on General Timing connection
Common hardware with BIS v2.
Draft timeline for SMP v2 development
Speaker
:
Raffaello Secondo
(
CERN
)
SMP2_Workshop_RSecondo_2.pdf
SMP2_Workshop_RSecondo_2.pptx
11:50
→
12:20
Wrap-up and Discussion
30m