PSB Commissioning Meeting #21 (PROBE/INDIV Production)
→
Europe/Zurich
774/1-014 (CERN)
Present: Fanouria, Alan, Chiara, Michele,GP, JF, Simon, Federico, Bettina, Piotr
- Action for all: check new version of chapter on optics measurements and corrections
- Piotr specified the need to have a Dp/p of 2E-3 for some of the optics measurements. According to initial specifications, 4.4e-3 RMS is the max Dp/p (energy swing). To be measured during LBE run.
- Document on Pre-LS2 beams to be filled by people appointed by Bettina. To be finished by this year (CERN note which might become a publication)
- LIU-CCC: tracking across the injector complex (machine specific data tracking and performance tracking per beam type). For PSB, different beams transverse and longitudinal emittance, ejected and extracted intensity, spill quality. What about losses? Sum of all ring BLMs and extraction and transfer? To be clarified with LIU-CCC if it can be considered a quality tracking
Simon - PROBE/INDIV production
From PSB beam commissioning meeting: losses during shaving for RP considerations, any optimisation possible to minimise the losses?
- It is possible getting the wished LHCINDIV intensity with one cavity
- Changing intensity requires to change also the injected length and the number of turns.
- Keep the specified emittance means changing the energy spread and/or the voltage.
- The chopper limits should be re-checked to evaluate the minimum allowed injected length.
Proposal: inject just a little extra-intensity and shave only what needed to reach the target.
Expected that all losses will occur at 200 MeV at the end of shaving, upper bound ~2E10 protons for operational beams.
If one considers 300 ns as minimum injected length one has to inject 4.5E10 and to get the PROBE (0.5E10) we would lose ~4E10.
For RP: losses for PROBE/INDIV production between 2E10-4E10.