The magnet should be delivered in mid-December, 2019. The objective is : Cold tests in February, 2020.
Minutes meeting 12.09.19
|
Tasks |
Responsible |
Informations |
|
Project |
P.Ferracin, S.Izquierdo Bermudez |
Delivered in December, 2019. The objective is cold tests in February, 2020. |
|
Cold mass |
H.Prin |
Hydraulical and electrical manifold installed by Herve Herve will do the “rallonge” from 18kA to 13kA busbars |
|
IFS, Instrumentation |
A.Foussat, J.Petrik |
2 * IFS close to CFB 50 Vtaps (66 – 16 missing) + 16 wires for heaters |
|
CRG instrumentation |
N.Vauthier |
3 temperature sensors |
|
Cryostating |
D.Duarte Ramos, O.Riu |
/ |
|
AC |
T.Lehtinen, M.Charrondière |
Design validated, AC manufacturing in progress, deadline 2.5 months |
|
Magnetic measurements |
L.Fiscarelli |
Project in progress but NO SHAFT (not ready for tests, discussion in progress to find solution) Stretched Wire could be used |
|
Drawings (Cryo-assembling) |
R.Betemps, Ph.Perret, R.Ferrière |
Waiting for drawing number to start thermal screens modification |
|
DRAWINGS (MSC-MM support) |
G.Villiger, F.Cottenot |
/ |
|
QPS |
J.Steckert |
Special protection meeting to schedule |
|
Protection |
E.Nowack, F.Rodriguez Mateos |
8 DQHDS + CLIQ : delivery expected to December, 2019 |
|
Strain gages, Optic fiber |
M.Guinchard, S.Emami Naini |
5 fischers 55 pins strain gages + 8 connectors Optic fibers |
|
Power convertors |
S.Yammine |
DCCT calibration mandatory before magnetic measurements |
|
CRG modifications |
G.Rolando |
Flowmeters in maintenance, DeltaT process upgrade in progress |
|
CRG operation |
JP.Lamboy |
Pressure test to perform on test bench |
|
Protection, PLC (MSC-TF) |
O.Ditsch, M.Charrondière |
Special protection meeting to schedule |
|
Tests |
G.Willering, F.Mangiarotti, G.Ninet |
Test plan : Nominal current, max 5 thermal cycles, 1.9K and 4.5K, current cycle, Ramp rate study, High Miits, Mag.measurememts |
|
Bench modification |
B.Mouches, A.Azarkan, F.Flamand |
CFB rotation and thermal screens removal done. Holes remain in yellow bench |
|
Miscellaneous |
|
Expected QH resistance at cold=5 W |
Gaëlle