MQXFBP1 Test Preparation

→ Europe/Zurich
sm18 (CERN)

sm18

CERN

Gaelle Ninet (CERN)

 

The magnet should be delivered in mid-December, 2019. The objective is :  Cold tests in February, 2020.

Minutes meeting 12.09.19

 

Tasks

Responsible

Informations

Project

P.Ferracin, S.Izquierdo Bermudez

Delivered in December, 2019. The objective is cold tests in February, 2020.

Cold mass

H.Prin

Hydraulical and electrical manifold installed by Herve

Herve will do the “rallonge” from 18kA to 13kA busbars

IFS, Instrumentation

A.Foussat, J.Petrik

2 * IFS close to CFB

50 Vtaps (66 – 16 missing) + 16 wires for heaters

CRG instrumentation

N.Vauthier

3 temperature sensors

Cryostating

D.Duarte Ramos, O.Riu

/

AC

T.Lehtinen, M.Charrondière

Design validated, AC manufacturing in progress, deadline 2.5 months

Magnetic measurements

L.Fiscarelli

Project in progress but NO SHAFT (not ready for tests, discussion in progress to find solution)

Stretched Wire could be used

Drawings (Cryo-assembling)

R.Betemps, Ph.Perret, R.Ferrière

Waiting for drawing number to start thermal screens modification

DRAWINGS (MSC-MM support)

G.Villiger, F.Cottenot

/

QPS

J.Steckert

Special protection meeting to schedule

Protection

E.Nowack, F.Rodriguez Mateos

8 DQHDS + CLIQ : delivery expected to December, 2019

Strain gages, Optic fiber

M.Guinchard, S.Emami Naini

5 fischers 55 pins strain gages + 8 connectors Optic fibers

Power convertors

S.Yammine

DCCT calibration mandatory before magnetic measurements

CRG modifications

G.Rolando

Flowmeters in maintenance, DeltaT process upgrade in progress

CRG operation

JP.Lamboy

Pressure test to perform on test bench

Protection, PLC (MSC-TF)

O.Ditsch, M.Charrondière

Special protection meeting to schedule

Tests

G.Willering, F.Mangiarotti, G.Ninet

Test plan : Nominal current, max 5  thermal cycles, 1.9K and 4.5K, current cycle, Ramp rate study, High Miits, Mag.measurememts

Bench modification

B.Mouches, A.Azarkan, F.Flamand

CFB rotation and thermal screens removal done.

Holes remain in yellow bench

Miscellaneous

 

Expected QH resistance at cold=5 W

 

Gaëlle

There are minutes attached to this event. Show them.