GIF++ installation and schedule meeting
-
-
09:15
→
09:35
Review of last week operation & plans for this week 20m
User Reports / Overview :
----------------------------------
ATLAS - sTGC : QS3 & QL1 finished. A test bench will be installed in the GIF++ preparation area. No chambers expected before November 7thATLAS-MM : SM1 long term in far down position removed. It will come back at some point for a long term study. A position as close as posbbile to the source, has to be find.
LM2-M9 & LM1-M9 installed on Wednesday 23rd. Gas bank connected.CMS-CSC: Electronic board troubles solved. Plan to change gas mixture. Chiller for the electronic setup and electronic rack cooling installed yesterday 23rd October
Setup from preparation area to be moved (bunker upstream or 904)EP-DT1: Stable conditions default 1. Fluoride measurements done. Will need still some months of irradiation.
EP-DT2 : Request to have the default value 2.2 in upstream.
CMS-DT: Rails back installed. Long one fixed to floor, other to be done.
Electronic racks needed mid-November.
Chamber expected to be installed end of year.
Request for field mapping at far end of bunker. To be scheduled - Currently planned for early November.EcoGas : Setup switched back On yesterday 23rd October.
CMS-RPC : iRPC and Trolley 3 in bunker. (Trolley 1 to come soon). Will try to have the scan at 46000 on Wednesday during the weekly access.
CMS-GEM : No report yet. Maybe leaving GIF.
ATLAS-RPC : Small prototype installed yesterday 23rd October. It will stay for 1-2 weeks
LHCb : working on the irradiated prototypes removed from GIF++ some months ago. Will be back in GIF++ most probably next year. A standalone gas line/supply will be needed this time.
==========================================================
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1
-------------------------------------------------------------------------------------------------------
-
09:35
→
09:40
Long Term Planing - General Items 5m
---------------------------------------------------------
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.
https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex
---------------------------------------------------------
To be scheduled : Stop of Gas supply for 2-3 days : to be scheduled (end of the year / beginning of next year)
---------------------------------------------------------
Next Irradiator maintenance : Proposal - January after Christmas Closure
-
09:40
→
09:50
New requests for tests at GIF 10m
introduction, goal of the test, plan, needs
FILTER BOX STUDY -> DONE.
Gas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)Bulgaria academy of science -> testing of new type of radiation monitor system
A new setup of ALICE-RPC will come. More news in coming weeks.
-
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)-
LS2 restrictions & interventions 5m
Upcoming :
=============PRIMARY & RAW WATER 2/2
• Status
-
– CT2 (Primary water) : Running until 18th Oct 19 and will be stopped until 15th Apr 20.
-
– BA81 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.
-
– BA82 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.
-
-
Cosmic Trigger 10m
-
-
10:00
→
10:30
Announcements 30m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
IMPACTS for 2019 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
-
-
09:15
→
09:35