AD-CONS Magnet WP Cost & Schedule review follow-up

→ Europe/Zurich
93/R-031 (CERN)

93/R-031

CERN

30
Show room on map

-Francois introduced the meeting by reminding the general LS2 work schedule at AD, in particular for what concerns the magnets refurbishment. The objectives of the review were to check the progress of the work, monitor the financial aspects and examine possible scope extension of the LS2 work.

 

-Antony reported on the accomplished work, that is following the agreed schedule: 14 out 24 dipoles in total have been treated so far. For LS2, the objective was to refurbish 10 dipoles and only 1 remains to be dealt with.

The quadrupoles refurbishment is also progressing according to schedule: 9 out of 28 in total have been treated so far. For LS2, the objective was to refurbish 9 quadrupoles and only 3 remain to be treated.

The current schedule shows that all refurbishment works should be complete by May 2020.

 

-The financial aspect was not discussed in detail as Lisette could not take part to the meeting. Nevertheless, it was checked in CET that the spending is in line with the allocated budget. 2020 foresees 15 kCHF in APT, which should be sufficient for ancillary works likely to be billed for the extraction /re-installation of the magnets (dismantling of barriers, floorboards etc).

 

-The AD technical coordination asked the magnet team whether it could be considered to extend the scope of the work during LS2 to treat a few other magnets. Antony explained that the work load with other machines does not allow to consider any extra work to be performed before July 2020, but it could be envisaged to add 1 or 2 dipoles and up to 4 quadrupoles to the scope of work. Nevertheless, it was noted that:

- Transport, vacuum and Survey were not present during the meeting.  Their input is required before any decision is made for the extension of the consolidation program.  If they have budget requests it shall be included in the consolidation request document.

- The scope of the extension initially discussed includes up to two bending magnets and four quadrupole magnets, however it is also possible to complete solely a part of this.  The priority is to refurbish the BHW20 as the shielding has already been dismantled to remove the BHW21.

- BE/OP have raised a concern for the schedule and the restart of the AD complex.  Based on previous experience, if starting in July TE/MSC would estimate that the two bending magnets will be returned to the AD machine by the end of October, the quadrupoles which are treated in a different workshop would be completed in parallel.  Input is required from transport, vacuum and survey as to their availability to complete the installation.  BE/OP will see if this fits with the schedule in terms of hardware testing etc, by providing a HW test schedule...

As a consequence, a decision is required by mid-January 2020 concerning the removal of the BHW20 as the main workshop could cut the vacuum chamber towards end of January.

BE-OP, TE-VSC, EN-SMM and EN-HE are requested to express their opinion regarding the above mentioned possible additional magnets to be treated.