ADTC / LS2 works follow-up MEETING

→ Europe/Zurich
93/R-031 (CERN)

93/R-031

CERN

30
Show room on map

General schedule (Francois):

The planning for the next weeks was presented, with the main info being that the cabling for ELENA will not resume on 18th May as requested. The restart date is not communicated yet (expected to be known on 27th May). The security work will nevertheless resume.(out of the meeting it was indicated that it won’t be possible to have the contractor on site on the 18th, the VIC will be held on 20th May, with work start most likely on 25th May).

The consequence on the subsequent work is not yet established. Re-shuffling of activities is being worked-out (in particular survey).

The good news is that the SEM acceptance test will resume as of 18th in lab, so installation should proceed as planned if no problem occurs.

 

SEM electronics tests (Mark): The tests performed on site were rather conclusive and Mark estimates that the electronics is now ready for order, although we can always perform more tests. He asked what is the latest date for populating the SEM with electronics. This is highly dependant on the overall schedule that is hanging from the cabling work. The tests that may be performed in the injection / ejection lines can be done with the 8 protos that are available.

 

LNE02 schedule (Mark):

The 3 phases of LNE02 installation are planned for mid June (ELENA side), November 2020 (Aegis side, with some preliminary work be needed as of September), January 2021 (both sides completion).

 

LNE02 SEM tank: The decision was made to install a normal SEM tank in position LNE.BSGWA.0225.

 

 

Francois BUTIN

Mobile: +41 75 411 0342

Francois.Butin@cern.ch

 

There are minutes attached to this event. Show them.