Cryo distribution line for AD experiments

→ Europe/Zurich
93/R-031 (CERN)

93/R-031

CERN

30
Show room on map

O. Pirotte reminded the objectives of the AD cryo line project, that are to optimize the delivery of cryogenic fluids to AD experiments, improving efficiency, reducing risks and logistics.

He reminded that the current limits in terms of lHe delivery capacities will not change (max 12000 l/week), and specificities of each experiment will be taken into account.

Overall material cost is estimate to 910 kCHF, on top of which personnel and control system cot should be added.

 

The project will be organized around 1 project leader (Olivier), 1 fellow with some experience in the cryo field (2.5 FTE to be financed by ALPHA as GET), and 1 draughtsman for integration and mechanical design (1 FTE to be supplied and financed by EN-EA) who will be coached by the fellow. TE-CRG will also provide the necessary support for the remaining aspects of the project. The cost of material will be covered by AD-CONS programme, with some 110 kCHF missing budget to be clarified (800 kCHF currently reserved in AD-CONS).

 

The proposed timeline is the following: 

Start of the studies : Oct 2020

Detailed design/Tech spec /tendering: 2021

Manufacturing / installation: 2022

Commissioning: 1st trimester 2023

 

The next steps are:

-issue an ECR and present it for approval to IEFC (Action Francois)

-identify potential candidates for the fellow position (Action Jeff + Olivier + Johan).

-clarify missing material budget question (Action Mike + Lisette + Markus)

There are minutes attached to this event. Show them.