Anticryostat du MQXFP1

→ Europe/Zurich
sm18 (CERN)

sm18

CERN

Gaelle Ninet (CERN)

- Quench antenna/Magnetic Measurements:

  • Components expected end of February
  • 1 week prepare PCBs
  • 1 week cabling in SM18

- DEMO2 uses the same power supply than MQXBP1. Preparation activities will proceed and decision  on priority will be taken at the time of the

- Peparation SM18: Delayed by two weeks with respect to the planning today, meaning that the magnet is in SM18 2nd March instead of 17th February. 

  • Short Anti-cryostat court (to be mounted in the CFB)
    • In assembly now (to be finished Feb 7th), ready to be delivered the week of 10-14 February. 
    • 40 kg, installation/manipulation should be feasible. A responsible within MSC group (staff) should be identified to coordinate activities/responsabilities.
  • Long Anti-cryostat (to be mounted in the magnet)
    • Thermal shields in fabrication in the main workshop. Components will arrive the week of 17th or 24th of February.
    • Charriot to be delivered to SMI2, can be delivered 13-14th February in order to do an insertion test. 
    • 17-24th February to develop in SMI2 the insertion procedure. 
    • Week 2nd-6th March magnet and anti-cryostat ready to be sent to SM18. Magnet will be transported without the anti-cryostat, but insertion will be simpler in SM18 (2 days should be enough in SM18)
  • Control will be tested by mid-February.                  